... flow contributed by the storage project , ( 3 ) the construction of additional steam electrical generating facilities , and ( 4 ) the construction of the new trans- mission facilities required on account of this added generating ...
... flow contributed by the storage project , ( 3 ) the construction of additional steam electrical generating facilities , and ( 4 ) the construction of the new trans- mission facilities required on account of this added generating ...
Page 9
... Watts Bar Dam has the effect of transforming a large amount of what is termed secondary or dump power resulting from the variations in the flow of the river into primary or continuous power which the TENNESSEE VALLEY AUTHORITY 9.
... Watts Bar Dam has the effect of transforming a large amount of what is termed secondary or dump power resulting from the variations in the flow of the river into primary or continuous power which the TENNESSEE VALLEY AUTHORITY 9.
Page 12
... flow ? Mr. DUNN . That is right . It equalizes the stream flow . I have no hesitation in recommending this particular water power develop- ment , because those are the facts . Mr. TABER . You mean that none of this water would come down ...
... flow ? Mr. DUNN . That is right . It equalizes the stream flow . I have no hesitation in recommending this particular water power develop- ment , because those are the facts . Mr. TABER . You mean that none of this water would come down ...
Page 14
... flow of the creek as a result of your increased storage , to your down - creek proposition . Mr. DUNN . That is right . I did not mean to say anything else than that . This is a huge storage reservoir . Mr. TABER . How big ? Mr. DUNN ...
... flow of the creek as a result of your increased storage , to your down - creek proposition . Mr. DUNN . That is right . I did not mean to say anything else than that . This is a huge storage reservoir . Mr. TABER . How big ? Mr. DUNN ...
Page 20
... flow is low , you have a steam plant to keep the power up to the equivalent of normal river flow you have validated a huge amount of power . REQUEST FOR COPY OF THE STETTINIUS REPORT Mr. DITTER . Mr. Stettinius , during the course of ...
... flow is low , you have a steam plant to keep the power up to the equivalent of normal river flow you have validated a huge amount of power . REQUEST FOR COPY OF THE STETTINIUS REPORT Mr. DITTER . Mr. Stettinius , during the course of ...
Common terms and phrases
additional Aluminum Co aluminum plant aluminum production amount of power approved Bonneville BUELL SNYDER CAPACITY OF T. V. A. Chairman Cherokee Dam Colonel PARKER COMMITTEE ON APPROPRIATIONS construction Defense Commission demands DITTER electric generating facilities EMMET O'NEAL engineers fiscal year 1941 Gano Dunn Government water power Holston Dam HOLSTON RIVER DAM hydro increased power installed capacity JOHN TABER JOHNSON of West July kilowatt-hour kilowatts KNUDSEN land LILIENTHAL LOUIS LUDLOW LUDLOW mean normal growth O'NEAL Pickwick units plane pounds of coal power capacity power increase power plant power supply present capacity private industry production of aluminum purchase question requirements reservoir statement Steam electric steam plant steam power STETTINIUS TABER Tenn Tennessee River Tennessee Valley Authority thing tion Total estimated cost transmission facilities ultimate capacity units at Wilson WESSENAUER West Virginia WIGGLESWORTH WILLIAM DITTER Willkie Wilson and Pickwick Wilson Dam WOODRUM
Popular passages
Page 30 - Tennessee Valley Authority fund, 1941": Provided further, That purchases may be made by the Authority during the fiscal year 1942 without regard to the provisions of section 3709 of the Revised Statutes and section 9 (b) of the Tennessee Valley Authority Act, as amended, when in the judgment of the Board of Directors of the Authority such a procedure will expedite the completion of projects determined by the President to...