Justice Department Investigations of Defense Procurement Fraud: A Case Study : a Staff Study |
From inside the book
Results 1-5 of 71
Page 7
... submarine claim and the entire aircraft carrier claim . Covington was assigned to a team but was not re- leased from his other Justice Department duties and did not " carry the ball " on any particular claim item or aspect of the case ...
... submarine claim and the entire aircraft carrier claim . Covington was assigned to a team but was not re- leased from his other Justice Department duties and did not " carry the ball " on any particular claim item or aspect of the case ...
Page 9
... Submarine , claim item . The Bow Dome report and its attachments were part of Norman's first report and re - submit- ted as part of the second report , discussed below . Norman states that the Bow Dome report provides a general overview ...
... Submarine , claim item . The Bow Dome report and its attachments were part of Norman's first report and re - submit- ted as part of the second report , discussed below . Norman states that the Bow Dome report provides a general overview ...
Page 100
... submarines constructed by Newport News in the period 1964 to 1969 , prior to CVN 68 Class contract definitization . The claim states that a reasonable quantity of discrepancy reports to expect for each CVN 68 Class vessel is 5,224 DR's ...
... submarines constructed by Newport News in the period 1964 to 1969 , prior to CVN 68 Class contract definitization . The claim states that a reasonable quantity of discrepancy reports to expect for each CVN 68 Class vessel is 5,224 DR's ...
Page 101
... submarines , cited as the basis for calculations in the claim . Contractual incorporation of MIL - Q - 9858A reflected Newport News ' continual upgrading of their nuclear quality control system throughout the 1960's . For example , in ...
... submarines , cited as the basis for calculations in the claim . Contractual incorporation of MIL - Q - 9858A reflected Newport News ' continual upgrading of their nuclear quality control system throughout the 1960's . For example , in ...
Page 102
... submarines . The Contractor erroneously treated the average number of DR's for five SSNs as the basis for projecting the maximum number which could " reasonably " be expected . The Contractor's use of prior SSN 637 Class submarine data ...
... submarines . The Contractor erroneously treated the average number of DR's for five SSNs as the basis for projecting the maximum number which could " reasonably " be expected . The Contractor's use of prior SSN 637 Class submarine data ...
Other editions - View all
Common terms and phrases
Adkins Admiral Rickover Alexandria allegations Aronica Bow Dome claim item Class compartment ventilation control conspiracy construction contract guidance drawing Contractor control air system Criminal Division CVAN Defense Delay Claimed Department of Justice diagram Discharge Sea Chests DLGN documents Dondich DPFU DR's Electric Boat employees equitable adjustment estimate evidence fact false claims false statement Fisher Fraud Section Glass Reinforced Plastic Government furnished grand jury indicated issued Justice Department letter manhours memo million MUDP's NAVSEA 08 Navy attorneys Navy's Newport News claims Newport News Shipbuilding Norman nuclear Ogren Paulisch Plant Lead Yard problems procurement fraud proposal prosecution prosecutors reactor compartment ventilation Reactor Plant Lead reference request Richmond Rickover shielding ships Shipway 9 shipyard Silverstein specifications staff statute of limitations submarines submitted target cost Tenneco theory tion U.S. Attorney United States Attorney valves VCAS ventilation control air Weiner white collar crime Willis
Popular passages
Page 29 - The test is whether the false statement has a natural tendency to influence, or was capable of influencing, the decision of the tribunal in making a determination required to be made.
Page 474 - Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change: Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may receive and act upon any such claim asserted at any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled "Disputes.
Page 474 - Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change: Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may receive and act upon any such claim asserted at any time prior to final payment under this contract.
Page 586 - Except as otherwise provided in this contract, the term "subcontracts" includes purchase orders under this contract. 2. CHANGES The Contracting Officer may at any time, by a written order, and without notice to the sureties, make changes, within the general scope of this contract, in any one or more of the following: (i) Drawings, designs, or specifications...
Page 557 - General. The fixed-price incentive contract is a fixed-price type contract with provision for adjustment of profit and establishment of the final contract price by a formula based on the relationship which final negotiated total cost bears to total target costs. (2) Firm Target. Under...
Page 834 - I certify that the claim is made in good faith; that the supporting data are accurate and complete to the best of my knowledge and belief; that the amount requested accurately reflects the contract adjustment for which the Contractor believes the Government is liable; and that I am duly authorized to certify the claim on behalf of the Contractor.
Page 756 - To conspire to defraud the United States means primarily to cheat the government out of property or money, but it also means to interfere with or obstruct one of its lawful governmental functions by deceit, craft, or trickery, or at least by means that are dishonest. It is not necessary that the government shall be subjected to property or pecuniary loss by the fraud, but only that its legitimate official action and purpose shall be defeated by misrepresentation, chicane, or the overreaching of those...
Page 670 - ... Opinion of the Court. MR. CHIEF JUSTICE TAFT delivered the opinion of the Court. This is a review by certiorari of the conviction of thirteen persons charged in one indictment with the crime of violating § 37 of the Penal Code. The charge was that the petitioners wilfully and unlawfully conspired to defraud the United States by impairing, obstructing and defeating a lawful function of its government, to wit: that of registering for military service all male persons between the ages of twenty-one...
Page 557 - ... final cost is more than target cost, application of the formula results in a final profit less than the target profit, or even a net loss Thus, within the price ceiling, the...
Page 750 - Intent ordinarily may not be proved directly, because there is no way of fathoming or scrutinizing the operations of the human mind.