(d) Decisions on OCIS. The contracting officer shall make recommendations to the General manager regarding disqualification or actions to be taken by the Board to avoid or mitigate any actual or potential OCI.

(1) The General Manager shall have the authority to approve, modify, or disapprove such recommendations regarding avoidance of an actual or potential OCI. If an offeror or contractor disagrees with the actions approved by the General Manager and requests review of the action, the Chairman shall make the decision on the actions to be taken by the Board.

(2) Any recommended action respecting the best interests of the Government and mitigation measures to be taken with respect to an actual or potential OCI must be approved by the Chairman in conjunction with the decision to grant a waiver pursuant to § 1706.8, and any recommended action $ to terminate a contract or a particular task on account of an actual or potential OCI must be approved by the Chairman.

(3) Decisions on OCIS by the General Manager or the Chairman shall be I made with the advice of the Office of the General Counsel.

[57 FR 44652, Sept. 29, 1992; 58 FR 13684, Mar. 12, 1993]

§ 1706.8 Waiver.

(a) Waiver of OCIS. The need for a waiver of any OCI in connection with the award or continuation of specific contracts may be identified either by the contracting officer for the Board or other Board employee or by a written request filed by an offeror or contractor with the contracting officer. The request may be combined with the certificate or disclosure required under §§ 1706.6 or 1706.7, or with additional statements filed under §1706.7 regarding matters raised in the certificate or disclosure. The contracting officer shall review all of the relevant facts brought to his attention and shall bring the matter to the General Manager, who shall make a written recommendation to the Chairman of the Board regarding whether a waiver should be granted for a contract award or for continuation of an existing contract.

(b) Criteria for Waiver of OCIS. (1) The Chairman is authorized to waive any OCI (and the corresponding provision of § 1706.5 where applicable) upon a determination that awarding or extending the particular contract, or not terminating the particular contract, would be in the best interests of the Government. Issuance of a waiver shall ordinarily be limited to those situations in which:

(i) The work to be performed under contract is vital to the Board program;

(ii) The work cannot be satisfactorily performed except by a contractor or offeror whose interests give rise to a question of OCI; and

(iii) Contractual and/or technical review and supervision methods can be employed by the Board to mitigate the conflict.

(2) The Chairman is also authorized to waive any OCI (and the corresponding provision of §1706.5 where applicable), without regard to the foregoing factors, if the Chairman determines, notwithstanding the existence of the OCI, that it is in best interests of the Government to award or extend the particular contract, or not to terminate it, without compliance with § 1706.8(b)(1).

(c) Waiver of Rules or Procedures. The Chairman is also authorized to waive any rules or procedures contained in this part upon a determination that application of the rules or procedures in a particular situation would not be in the best interests of the Government. Any request for such a waiver must be in writing and shall describe the basis for the waiver.

(d) Office of General Counsel. Waivers of OCIS or of any rule or procedure contained in this part shall be made after consultation with the Office of General Counsel.

(e) Federal Register. Except as otherwise provided in §1706.8(c), notice of each waiver granted under this section shall be published in the FEDERAL REGISTER with an explanation of the basis for the waiver. In the discretion of the Board, notices of instances of avoidance of OCIs may also be published in the FEDERAL REGISTER.

$1706.9 Examples.

The examples in this section illustrate situations in which questions concerning OCIs may arise. The examples are not all inclusive, but are intended to provide offerors and contractors with guidance on how this subpart will be applied.

(a) Circumstances (1) Facts. A Board contractor for technical assistance in the review of a safety aspect of a particular defense nuclear facility proposes to use the services of an expert who also serves on an oversight committee for a contractor of other defense nuclear facilities.

(2) Guidance. Assuming the work of the oversight committee has no direct or indirect relationship with the work at the facility that is the subject of the Board's contract, there would not be an OCI associated with the use of this expert in the performance of the Board contract.

(b) Circumstances (1) Facts. A Board contractor studying the potential for a chemical explosion in waste tanks at a defense nuclear facility advises the Board that it has been offered a contract with DOE to study the chemical composition of the waste in the same tanks.

(2) Guidance. The contractor would be advised that accepting the DOE contract would result in termination of its performance under its contract with the Board.

(c) Circumstances (1) Facts. The Board issues a task order under an existing contract for the evaluation of the adequacy of fire protection systems at a defense nuclear facility. The contractor then advises the Board that it is considering making an offer on a solicitation by DOE to evaluate the same matter.

(2) Guidance. The contractor would be advised that entering into a contract with DOE on that solicitation could result in the contract with the Board being terminated.

(d) Circumstances (1) Facts. A firm responding to a formal Board solicitation for technical assistance provides information regarding a contract it currently has with DOE. The effort under the DOE contract is for technical assistance work at DOE facilities not

subject to Board oversight and outside its jurisdiction.

(2) Guidance. The Board would analyze the work being performed for DOE to ensure no potential or actual conflict of interest would be created through award of the Board contract. Should the Board determine that no potential or actual conflict of interest exists, the contractor would be eligible for award. If the Board determines that a potential or actual conflict of interest would arise through a contract award, it may disqualify the firm or, if the Board determines that such action is in the best interests of the Government, the Board may waive the conflict or the rules and procedures and proceed with the award.

(e) Circumstances—(1) Facts. The Board discovers that a firm competing for a contract has a number of existing agreements with DOE in technical areas which are unrelated to the Board's oversight authority. While these contracts may not represent a potential or actual conflict of interest regarding the substance of the technical effort, their total value constitutes a significant portion of the firm's gross revenues.

(2) Guidance. A conflict of interest may exist due to the firm's substantial pecuniary dependence upon DOE. Consequently, the Board may question the likelihood that the contractor would provide unbiased opinions, conclusions, and work products because of this extensive financial relationship. The Board will review and consider the extent of the firm's financial dependence on DOE, the nature of the proposed Board contract, the need by the Board for the services and expertise to be provided by the firm and the availability of such services and expertise elsewhere, and whether the likelihood of the firm's providing objective technical evaluations and opinions to the Board could be influenced in view of its DOE relationship. Based on this analysis, the Board may either determine that there is no conflict and make the award, waive the conflict if one is identified and establish procedures to mitigate it where possible, or disqualify the offeror.

(f) Circumstances-(1) Facts. The Board discovers that a firm competing

for a contract has a substantial business relationship in technical areas unrelated to the Board's oversight authority with a contractor operating a defense nuclear facility under a DOE contract. Similar to the situation described in paragraph (e) of this section, the total value of the contracts with the DOE contractor constitutes more than half of the firm's gross revenues, even though those contracts do not represent a potential or actual conflict of interest regarding any of the particular matters to be covered by the contract with the Board.

(2) Guidance. The firm's substantial financial and business dependence upon the DOE contractor may give rise to a conflict of interest, in that the likelihood of the firm's rendering impartial, objective assistance or advice to the Board may be impaired by its extensive financial relationship with the DOE contractor. In this situation, the Board will review and consider the nature of the proposed Board contract, the need by the Board for the services and expertise to be provided by the firm and the availability of such services and expertise elsewhere. The Board will also review and consider the extent of the firm's financial dependence on the DOE contractor and whether the firm would be impartial and objective in evaluation providing technical and

opinions to the Board, especially on matters in which the DOE contractor is involved, notwithstanding the relationship with the DOE contractor. Based on this analysis, the Board may determine that there is no actual conflict of interest and make the award. Alternatively, if the Board identifies a conflict that cannot be avoided, the Board may determine to waive the conflict in the best interests of the United States, with or without the establishment of procedures to mitigate the conflict, or it may disqualify the offer

[blocks in formation]

disqualification of the offeror for that award. The nondisclosure or misrepresentation of any relevant information may also result in the disqualification of the offeror for that award. If such nondisclosure or misrepresentation by an offeror or contractor is discovered or occurs after award, or in the event of breach of any of the restrictions contained in this part, the Board may terminate the contract for convenience or default, and the offeror or contractor may also be disqualified by the Board from consideration for subsequent Board contracts and be subject to such other remedial actions as provided by law or the contract.

[57 FR 44652, Sept. 29, 1992; 58 FR 13684, Mar. 12, 1993]

[blocks in formation]

(a) An organizational or consultant conflict of interest means that because of other activities or relationships with other persons, a person is unable or potentially unable to render impartial assistance or advice to the Government, or the person's objectivity in performing the contract work is or might be otherwise impaired, or a person has an unfair competitive advantage.

(b) In order to comply with the Office of Federal Procurement Policy Letter 89-1, Conflict of Interest Policies Applicable to Consultants, the offeror shall provide the certificate described in paragraph (c) of this provision.

(c) The certificate must contain the following:

(1) Name of the agency and the number of the solicitation in question.

(2) The name, address, telephone number, and federal taxpayer identification number of the offeror.

(3) A description of the nature of the services rendered by or to be rendered on the instant contract.

(4) The name, address, and telephone number of the client or clients, a description of the services rendered to the previous client(s), and the name of a responsible officer or employee of the offeror who is knowledgeable about the services rendered to each client, if, in the 12* months preceding the date of the certification, services were rendered to the Government or any other client (including a foreign government or person) respecting the same subject matter as the instant solicitation, or directly relating to such subject matter. The agency and contract number under which the services were rendered must also be included, if applicable.

(5) A statement that the person who signs the certificate has made inquiry and that, to the best of his or her knowledge and belief, no actual or potential conflict of interest or unfair competitive advantage exists with respect to the advisory or assistance services to be provided in connection

with the instant contract, or that any actual or potential conflict of interest or unfair competitive advantage that does or may exist with respect to the contract in question has been communicated in writing to the contracting officer or his or her representative; and

(6) The signature, name, employer's name, address, and telephone number of the person who signed the certificate.

(d) Persons required to certify but who fail to do so may be determined to be nonresponsible. Misrepresentation of any fact may result in suspension or debarment, as well as penalties associated with false certifications or such other provisions provided for by law or regulation.

[End of provision]

* If approved by the head of the contracting activity, this period may be increased up to 36 months.

11

CHAPTER XVIII-NORTHEAST INTERSTATE LOWLEVEL RADIOACTIVE WASTE COMMISSION

Part 1800

Page

Declaration of Party State Eligibility for North-
east Interstate Low-Level Radioactive Waste
Compact

895