provides the maximum possible reduction of pollution;

(5) An examination of the environmental compliance of the facility, including an analysis of its ability to meet applicable standards and criteria when using both the proposed fuel and the alternate fuel(s) which would provide the basis for the exemption. All such analysis must be based on accepted analytical techniques, such as air quality modeling, and reflect current conditions of the area which would be affected by the facility. The petitioner is responsible for obtaining the necessary data to accurately characterize these conditions. Environmental compliance must be examined in the context of available pollution control equipment which would provide the maximum possible reduction of pollution. The analysis must contain: (i) Requests for bids and other inquiries made and responses received by the petitioner concerning the availability and performance of pollution control equipment; or (ii) other comparable evidence such as technical studies documenting the efficacy of equipment to meet applicable requirements;

(6) An examination of any regulatory options available to the petitioner in seeking to achieve environmental compliance (such as offsets, variances and State Implementation Plan (SIP) revisions); and

(7) Any other documentation which demonstrates an inability to comply with applicable environmental requirements;

(8) No alternate power supply exists as required under §503.8 of these regulations;

(9) Use of mixtures is not feasible, as required under §503.9 of these regulations;

(10) Alternative sites are not available, as required under § 503.11 of these regulations;

(11) Environmental impact analysis, as required under § 503.13 of these regulations; and

(12) Fuels search, as required under § 503.14 of these regulations.

(d) Certification alternative. (1) To qualify for this exemption, in lieu of meeting the evidentiary requirements of paragraph (c) of this section, a petitioner may certify that:

(i) The site for the facility is or will be located in a Class I area or Class II area in which the allowable increment established by law has been consumed, as defined in part C of the Clean Air Act; the use of an alternate fuel will cause or contribute to concentrations of pollutants which would exceed the maximum allowable increases in a Class I or Class II area even with the application of best available control technology; the site for the facility is or will be located in a non-attainment area as defined in part D of the Clean Air Act for any pollutant which would be emitted by the facility; or, even with the application of the lowest achievable emission rate, the use of an alternate fuel will cause or contribute to concentrations in an air quality control region of a pollutant for which any national ambient air quality standard is or would be exceeded;

(ii) No alternate power supply exists, as required under §503.8 of these regulations;

(iii) Alternative sites are not available, as required under § 503.11 of these regulations; and

(iv) Use of mixtures is not feasible, as required under § 503.19 of these regulations.

(2) A petition by certification under this paragraph must include:

(i) Duly executed certifications required under paragraph (d)(1) of this section;

(ii) Exhibits containing the basis for the certifications required under paragraph (d)(1) of this section (including those factual and analytical materials deemed by the petitioner to be sufficient to support the granting of this exemption);

(iii) Environmental impact analysis, as required under § 503.13 of these regulations; and

(iv) Fuels search, as required under § 503.14 of these regulations.

[46 FR 59903, Dec. 7, 1981, as amended at 54 FR 52895, Dec. 22, 1989]

§ 503.35 Inability to obtain adequate capital.

(a) Eligibility. Section 212(a)(1)(D) of the Act provides for a permanent exemption due to inability to obtain adequate capital. To qualify, a petitioner must certify that:

(1) Despite good faith efforts the petitioner will be unable to comply with the applicable prohibitions imposed by the Act because the additional capital required for an alternate fuel-capable unit beyond that required for the proposed unit cannot be raised;

(2) The additional capital cannot be raised:

(i) Due to specific restrictions (e.g., convenants on existing bonds) which constrain management's ability to raise debt or equity captial;

(ii) Without a substantial dilution of shareholder equity;

(iii) Without an unreasonably adverse affect on the utility's credit rating; or (iv) In the case of non-investor-owned public utilities, without jeopardizing the utility's ability to recover its capital investment, through tariffs, without unreasonably adverse economic effect on its service area (such as adverse impacts on local industry or undue hardship to ratepayers).

(3) No alternative power supply exists, as required under $503.8 of these regulations;

(4) Use of mixtures is not feasible, as required under $503.9 of these regulations; and

(5) Alternative sites are not available, as required under §503.11 of these regulations.

(b) Evidence required in support of a petition. A petition must include the following evidence in order to make the demonstration required by this section:

(1) Duly executed certifications required under paragraph (a) of this section;

(2) Exhibits containing the basis for the certifications required under paragraph (a) of this section (including those factual and analytical materials deemed by the petitioner to be sufficient to support the granting of this exemption);

(3) Environmental impact analysis, as required under § 503.13 of these regulations; and

(4) Fuels search, as required under § 503.14 of these regulations.

[46 FR 59903, Dec. 7, 1981, as amended at 47 FR 15315, Apr. 9, 1982; 54 FR 52895, Dec. 22, 1989]

§ 503.36 State or local requirements.

(a) Eligibility. Section 212(b) of the Act provides for an exemption due to certain State or local requirements. To qualify a petitioner must certify that:

(1) With respect to the proposed site of the unit, the operation or construction of the new unit using an alternate fuel is infeasible because of a State of local requirement other than a building code, nuisance, or zoning law;

(2) The petitioner has made a good faith effort to obtain a variance from the State or local requirement but has been unable to do so or has demonstrated why none is available;

(3) The granting of the exemption would be in the public interest and would be consistent with the purposes of the Act;

(4) The petitioner is not entitled to an exemption for lack of alternate fuel supply, site limitation, environmental requirements, or inability to obtain adequate capital at the site of the proposed powerplant or at any reasonable alternative site for the alternate fuel(s) considered;

(5) At the proposed site and every reasonable alternative site where the petitioner is not entitled to an exemption for lack of alternate fuel supply, site limitation, environmental requirements, or inability to obtain adequate capital, the petitioner nevertheless would be barred at each such proposed or alternate site from burning an alternate fuel by reason of a State or local requirement;

(6) No alternate power supply exists, as required under §503.8 of these regulations; and

(7) Use of mixtures is not feasible, as required under §503.9 of these regulations.

(b) Evidence required in support of a petition. The petition must include the following evidence in order to make the demonstration required by this section:

(1) Duly executed certifications required under paragraph (a) of this section;

(2) Exhibits containing the basis for the certifications required under paragraph (a) of this section (including those factual and analytical materials

194-031 D-01--3

[blocks in formation]
[blocks in formation]

Data are based upon 1987 oil, natural gas and electricity statistics published by DOE's Energy Information Administration.

EXAMPLE: The proposed cogeneration project is to be located in Massachusetts and is to use distillate oil. It will have a capacity of 50 MW, an average annual heat rate of 7600 BTU/KWHR, and be operated at a capacity factor of 90%. The annual fuel consumption is therefore calculated to be 2,996×109 Btu/yr. (50,000 KW 7600 BTU/KWHR-.9×8760 HR/YR) The oil and gas backed off the grid would be calculated to be .2070×109 BTU/YR. (50,000 KW×5250 BTU/KWHR-.9×8760 HR/YR) since the proposed unit would consume more oil that would be "backed off" the grid, the unit would not be eligible for a permanent exemption based on savings of oil and natural gas. [54 FR 52895, Dec. 22, 1989]

§ 503.38 Permanent exemption for certain fuel mixtures containing natural gas or petroleum.

(a) Eligibility. Section 212(d) of the Act provides for a permanent exemption for certain fuel mixtures. To qualify a petitioner must certify that:

(1) The petitioner proposes to use a mixture of natural gas or petroleum and an alternate fuel as a primary energy source;

(2) The amount of petroleum or natural gas proposed to be used in the mixture will not exceed the minimum percentage of the total annual Btu heat input of the primary energy sources needed to maintain operational reliability of the unit consistent with maintaining a reasonable level of fuel efficiency; and

(3) No alternate power supply exists, as required under § 503.8 of these regulations.

(b) Evidence required in support of a petition. The petition must include the following evidence in order to make

the demonstration required by this section:

(1) Duly executed certifications required under paragraph (a) of this section;

(2) Exhibits containing the basis for the certifications required under paragraph (a) of this section (including those factual and analytical materials deemed by the petitioner to be sufficient to support the granting of this exemption);

(3) A description of the fuel mixture, including component fuels and the percentage of each such fuel to be used; and

(4) Environmental impact analysis as required under § 503.13 of these regulations.

(c) Solar mixtures. OFE will grant a permanent mixtures exemption for the use of a mixture of solar energy (including wind, tide, and other intermittent sources) and petroleum or natural gas, where:

(1) Solar energy will account for at least 20 percent of the total annual Btu heat input, of the primary energy sources of the unit; and

(2) Petitioner meets the eligibility and evidentiary requirements of paragraphs (a) and (c) of this section.

[46 FR 59903, Dec. 7, 1981, as amended at 54 FR 52896, Dec. 22, 1989]

§§ 503.39-503.44 [Reserved]

PART 504-EXISTING POWERPLANTS

504.2 Purpose and scope. 504.3-504.4 [Reserved]

504.5 Prohibitions by order (certifying powerplants under section 301 of FUA, as amended).

504.6 Prohibitions by order (case-by-case). 504.7 Prohibition against excessive use of petroleum or natural gas in mixtureselecting powerplants.

504.8 Prohibitions against excessive use of petroleum or natural gas in mixturescertifying powerplants.

504.9 Environmental requirements for certifying powerplants.

APPENDIX I TO PART 504-PROCEDURES FOR

THE COMPUTATION OF THE REAL COST OF
CAPITAL

APPENDIX II TO PART 504-FUEL PRICE COM-
PUTATION

AUTHORITY: Department of Energy Organization Act, Pub. L. 95-91, 91 Stat. 565 (42

U.S.C. §7101 et seq.); Powerplant and Industrial Fuel Use Act of 1978, Pub. L. 95-620, 92 Stat. 3289 (42 U.S.C. 8301 et seq.); Energy Security Act, Pub. L. 96-294, 94 Stat. 611 (42 U.S.C. 8701 et seq.); E.O. 1209, 42 FR 46267, Sept. 15, 1977.

SOURCE: 45 FR 53692, Aug. 12, 1980, unless otherwise noted.

(Approved by the Office of Management and Budget under control number 1903-0075. See 46 FR 63209, Dec. 31, 1981.)

$504.2 Purpose and scope.

(a) Sections 504.5, 504.6, and 504.8, set forth the prohibitions that OFP, pursuant to section 301 of the Act, as amended, may impose upon existing powerplants after a review of the certification and prohibition order compliance schedule submitted by the owner or operator of a powerplant. Sections 504.5 and 504.8 are explanatory sections, and $504.6 provides the informational requirements necessary to support the certification.

(b) Sections 504.6 and 504.7, set forth the prohibitions that OFP may impose upon certain electing powerplants, pursuant to former section 301 (b) and (c) of FUA, where OFP can make the findings as to the unit's technical capability and financial feasibility to use coal or another alternate fuel as a primary energy source. The prohibitions may be made to apply to electing powerplants unless an exemption is granted by OFP under the provisions of the Final Rule for Existing Facilities (10 CFR parts 500, 501 and 504) published at 45 FR 53682, Aug. 12, 1980 and 46 FR 59872, Dec. 7, 1981. Any person who owns, controls, rents or leases an existing electing powerplant may be subject to the prohibitions imposed by and the sanctions provided for in the Act or these regulations, if OFP can make the findings required by former section 301 (b) and (c) of FUA.

(Department of Energy Organization Act, Pub. L. 95-91, 91 Stat. 565 (42 U.S.C. 7101 et seq.); Powerplant and Industrial Fuel Use Act of 1978, Pub. L. 95-620, 92 Stat. 3269 (42 U.S.C. 8301 et seq.); Omnibus Budget Reconciliation Act of 1981, Pub. L. 97-35; E.O. 12009, 42 FR 46267, Sept. 15, 1977) [47 FR 50849, Nov. 10, 1982]

§§ 504.3-504.4 [Reserved]

$504.5 Prohibitions by order (certifying powerplants under section 301 of FUA, as amended).

(a) In the case of existing powerplants, OFP may prohibit, in accordance with section 301 of the Act, as amended, the use of petroleum or natural gas as a primary energy source where the owner or operator of the powerplant presents a complete certification concurred in by OFP. The certification, which may be presented at any time, pertains to the unit's technical capability and financial feasibility to use coal or another alternate fuel as a primary energy source in the unit. The informational requirements necessary to support a certification are contained in §504.6 of these regulations. A prohibition compliance schedule which meets the requirements of § 504.5(d) shall also be submitted.

(b) If OFP concurs with the certification, a prohibition order on the powerplant's use of petroleum or natural gas will be issued following the procedure outlined in § 501.52 of these regulations.

(c) The petitioner may amend its certification at any time prior to the effective date of the prohibitions contained in the final prohibition order in order to take into account changes in relevant facts and circumstances by following the procedure contained in § 501.52(d).

(d) Prohibition order compliance schedule. The certification described above, which forms the basis for the issuance of a prohibition order to a powerplant, shall include a prohibition order compliance schedule. The compliance schedule should contain the following:

(1) A schedule of progressive events involved in the conversion project, including construction of any facilities for the production of fuel or fuel handling equipment, and contracts for the purchase of alternate fuels, and estimated date of compliance with the applicable prohibitions of the Act; and

(2) A schedule indicating estimated dates for obtaining necessary federal, state, and local permits and approvals. Any prohibition order issued under the certification provisions of §§ 504.5, 504.6, and 504.8 will be subject to appropriate

conditions subsequent so as to delay the effectiveness of the prohibitions contained in the final prohibition order until the above events or permits have occurred or been obtained.

(Approved by the Office of Management and Budget under control number 1903-0077) (Department of Energy Organization Act, Pub. L. 95-91 (42 U.S.C. 7101 et seq.); Energy Supply and Environmental Coordination Act of 1974, Pub. L. 93-319, as amended by Pub. L. 94-163, Pub. L. 95-70, and Pub. L. 95-620 (15 U.S.C. 719 et seq.); Powerplant and Industrial Fuel Use Act of 1978, Pub. L. 95-620, as amended by Pub. L. 97-35 (42 U.S.C. 8301 et seq.); Omnibus Budget Reconciliation Act of 1981, Pub. L. 97-35)

[47 FR 17044, Apr. 21, 1982]

§ 504.6 Prohibitions by order (case-bycase).

(a) OFP may prohibit, by order, the use of natural gas or petroleum as a primary energy source in existing powerplants under certain circumstances. In the case of certifying powerplants under section 301 of the Act, as amended, the petitioner must present evidence to support the certification, required by $504.6 (c), (d), (e), and (f). In the case of electing powerplants, OFP must make the following findings required by §504.6 (c), (d), (e), and (f), in order to issue a prohibition order to the unit, pursuant to former section 301 (b) or (c):

(1) The unit currently has, or previously had, the technical capability to use an alternate fuel as a primary energy source;

(2) The unit has this technical capability now, or it could have the technical capability without:

(i) A substantial physical modification of the unit; or

(ii) A substantial reduction in the rated capacity of the unit; and

(3) It is financially feasible for the unit to use an alternate fuel as its primary energy source.

(b) In the case of electing powerplants, OFP must make a proposed finding regarding the technical capability of a unit to use alternate fuel as identified in paragraph (a) (1) of this section prior to the date of publication of the notice of the proposed prohibition. OFP will publish this finding in