Page 5
... further steps or appeal in connection with that suspension . The plaintiff contends as follows : ( 1 ) The United States District Court and the Civil Service Commission were pre- sented with identical charges . The District Court ...
... further steps or appeal in connection with that suspension . The plaintiff contends as follows : ( 1 ) The United States District Court and the Civil Service Commission were pre- sented with identical charges . The District Court ...
Page 6
... further recites that the " basic evidence secured through the agency's in- vestigation , as shown by the report of Special Agents Sweeney and Smith , dated March 28 , 1952 , is concerned with the alleged extortion of $ 7,000 from the ...
... further recites that the " basic evidence secured through the agency's in- vestigation , as shown by the report of Special Agents Sweeney and Smith , dated March 28 , 1952 , is concerned with the alleged extortion of $ 7,000 from the ...
Page 7
... further evidence to submit to the Com- mission indicates that he had substantially full information . The defendant further asserts the defense of laches , claim- ing that the plaintiff did not file his petition in this court until 311 ...
... further evidence to submit to the Com- mission indicates that he had substantially full information . The defendant further asserts the defense of laches , claim- ing that the plaintiff did not file his petition in this court until 311 ...
Page 8
... further held that defendant is entitled to recover on its third counterclaim to the extent of interest on overpayments ultimately recouped from the contractor . 8 Syllabus Contracts ; fraud against the United States ; 8 S. HARVEY KLEIN ...
... further held that defendant is entitled to recover on its third counterclaim to the extent of interest on overpayments ultimately recouped from the contractor . 8 Syllabus Contracts ; fraud against the United States ; 8 S. HARVEY KLEIN ...
Page 12
... further said that Beam's available space was inadequate for the timely assembling of the lighting sets , and that Beam's financing was not sufficient for the performance of the contract . On June 4 , 1952 , Beam appealed the contracting ...
... further said that Beam's available space was inadequate for the timely assembling of the lighting sets , and that Beam's financing was not sufficient for the performance of the contract . On June 4 , 1952 , Beam appealed the contracting ...
Other editions - View all
Common terms and phrases
action active duty agreement aluminum amount approval Army assets August Beam Bureau Canal claim Commission Commissioner Company computed contract 955 Contracting Officer Contractor corporation Correction Board cost Court 152 Ct defendant defendant's determined disability retired District dredging easement excess profits excess profits tax Fact 152 Ct filed Findings of Fact follows Freedom Fair Government income interest Internal Revenue Internal Revenue Code January January 18 Judge judgment July June June 27 Kaiser land lease lessee letters of intent liability Liberty ships Maritime Maritime Commission ment military Navy November October October 20 October 31 operation Opinion paid percent period petition physical disability piles plaintiff plants prior pursuant quay wall received record refund requested res judicata retired list retired pay Reynolds riprap rocky fill Sea Trader ships Sol Goldenberg Stat statute summary judgment termination tion transfer Troutdale United vessels Wiegand
Popular passages
Page 466 - ... Corporations, and any community chest, fund, or foundation, organized and operated exclusively for religious, charitable, scientific, testing for public safety, literary, or educational purposes, or for the prevention of cruelty to children or animals, no part of the net earnings of which inures to the benefit of any private shareholder or individual, no substantial part of the activities of which is carrying on propaganda, or otherwise attempting, to influence legislation, and which does not...
Page 206 - All transfers and assignments made of any claim upon the United States, or of any part or share thereof, or interest therein, whether absolute or conditional, and whatever may be the consideration therefor, and all powers of attorney, orders, or other authorities for receiving payment of any such claim, or of any part or share thereof, shall be absolutely null and void...
Page 207 - ... after the allowance of such a claim, the ascertainment of the amount due and the issuing of a warrant for the payment thereof.
Page 171 - The rights and remedies of the Government provided in this clause shall not be exclusive and are In addition to any other rights and remedies provided by law or under this contract.
Page 37 - Take such action as may be necessary, or as the Contracting Officer may direct, for the protection and preservation of the property related to this contract which is in the possession of the Contractor and In whicn the Government has or may acquire an interest.
Page 833 - In the case of a failure to make and file a declaration of estimated tax within the time prescribed, unless such failure is shown to the satisfaction of the Commissioner to be due to reasonable cause and not to willful neglect...
Page 38 - Such claim shall be submitted promptly but in no event later than one year from the effective date of termination, unless one or more extensions in writing are granted by the Contracting Officer, upon request of the Contractor made in writing within such one year period or authorized extension thereof.
Page 41 - Contractor, from the effective date of termination and for a period of three years after final settlement under this contract, shall preserve and make available to the Government at all reasonable times at the...
Page 37 - ... terminate all orders and subcontracts to the extent that they relate to the performance of work terminated by the Notice of Termination...
Page 16 - The performance of work under this contract may be terminated by the Government in accordance with this clause in whole, or from time to time in part, whenever the Contracting Officer shall determine that such termination is in the best interest of the Government.