Specifications, Schedule, and Drawings: Hoover Dam, Power Plant and Appurtenant Works. Boulder Canyon Project. Arizona-California-Nevada ... |
From inside the book
Results 1-5 of 44
Page 15
... addition to the drainage galleries there will be a number of inspection galleries. Two elevator shafts with adits at the elevation of the generator floor of the power house will connect the two wings of the power house with the top of ...
... addition to the drainage galleries there will be a number of inspection galleries. Two elevator shafts with adits at the elevation of the generator floor of the power house will connect the two wings of the power house with the top of ...
Page 18
... additional drawings showing details of the work will be fur. to the contractor during the progress of the work. The contractor will be furnished such additional copies of the *Pecifications and drawings as may be required for carrying ...
... additional drawings showing details of the work will be fur. to the contractor during the progress of the work. The contractor will be furnished such additional copies of the *Pecifications and drawings as may be required for carrying ...
Page 19
... additional power units on each side of the river immediately downstream from the other power units, up to elevation 660; and all other portions of the power plant and other works which must be completed before the necessary power ...
... additional power units on each side of the river immediately downstream from the other power units, up to elevation 660; and all other portions of the power plant and other works which must be completed before the necessary power ...
Page 22
... Additional drilling is in progress at the date of the issuance of these specifications and available information, including logs of holes and drill cores, for all of the drilling done, will be available for the information of bidders ...
... Additional drilling is in progress at the date of the issuance of these specifications and available information, including logs of holes and drill cores, for all of the drilling done, will be available for the information of bidders ...
Page 23
... additional cost to the Government. - 34. Use of Boulder City as camp site.—Owing to the inaccessibility of the work, the magnitude of the operations, and the severe weather conditions during a large part of the year on account of ...
... additional cost to the Government. - 34. Use of Boulder City as camp site.—Owing to the inaccessibility of the work, the magnitude of the operations, and the severe weather conditions during a large part of the year on account of ...
Common terms and phrases
acceptance accordance additional adits amount approved bars bond cement cleaned cofferdam completed concrete conduit connection construction contracting officer contractor covered damage DEPARTMENT deposits described determined directed diversion tunnels downstream drawings drilled elevator equipment excavation expense face feet finished fittings floor Flow Breccia forms foundation furnished gates Government gravel grout gunite handling hauling highway hoists holes inch inclined include the cost installing intake towers joints length less lining located manner materials measured metal necessary º º operation otherwise outlet paint paragraph paragraph 27 payment permitted pipe placed plant plates plugs portions pounds power house pressure protection provided in paragraph provisions of paragraph railroad removed river rock sand satisfactory schedule shafts shown side specifications spillway square standard steel structures sufficient suitable surface therefor thickness tile unit prices bid upstream valves yard
Popular passages
Page 30 - The property shall be returned in as good condition as when received, reasonable wear and tear excepted.
Page 19 - That all persons who hav.e served in the United States Army, Navy, or Marine Corps during the war with Germany, the war with Spain, or in the suppression of the insurrection...