Page images
PDF
EPUB

105.04 Coordination of Specifications. The General Provisions, Special Provisions, Plans, Supplemental Specifications, Standard Specifications, and all supplemental documents affecting the work, duly issued by the Engineer to the Contractor, are essential parts of the contract, and a requirement occurring in one is as binding as if occurring in all. They are intended to be complementary and to describe and provide for a complete work. In case of discrepancy, numerical dimensions will prevail over scaled dimensions and the parts of the contract will prevail in the following order:

1. General Provisions (SF 23A)

2. Special Provisions

3. Plans

4. Supplemental Specifications

5. Standard Specifications

In Clause 2, of SF 23A the term "specifications” is interpreted to mean job specifications of a nature corresponding to "special provisions”, as defined in subsection 101.02 and not the standard specifications that are of general application.

The Contractor shall take no advantage of any apparent error or omission in the plans or specifications. In the event the Contractor discovers such an error or omission, he shall immediately notify the Engineer. The Engineer will then make such corrections and interpretations as may be deemed necessary for fulfilling the intent of the plans and specifications.

105.05 Cooperation by Contractor. The Contractor will be supplied with a minimum of two sets of approved plans and contract assemblies including special provisions.

See SF 23A, General Provisions.

105.06 Cooperation with Utilities. The Government will notify all utility companies, all pipe line owners or other parties affected, and endeavor to have all necessary adjustments of the public or private utility fixtures, pipe lines, and other appurtenances within or adjacent to the limits of construction, made as soon as practicable.

Water lines, gas lines, wire lines, service connections, water and gas meter boxes, water and gas valve boxes, light standards, cableways, signals, and all other utility appurtenances within the limits of the proposed construction which are to be relocated or adjusted are to be moved by others at their expense, unless otherwise provided in the contract.

It is understood and agreed that the Contractor has considered in his bid all of the permanent and temporary utility appurtenances in their present or relocated positions as shown on the plans and that no additional compensation will be allowed for any delays, inconvenience, or damage sustained by him due to any interference from the said utility appurtenances or the operation of moving them.

Note: The contract may indicate various utility items, certain of which are to be relocated or adjusted by the utility owner and others

which are to be relocated or adjusted by the Contractor. The provisions will indicate the means of adjudication, if any, in failure by the utility owners to comply with their responsibi relocating or adjusting their facility.

105.07 Other Contracts.

See SF23A General provisions.

105.08 Construction Stakes, Lines and Grades. The En will set such initial construction stakes establishing lines, slope continuous profile-grade in road work, and reference lines and marks for bridge work, culvert work, protective and accessory tures and appurtenances as he may deem necessary, and will f the Contractor with all necessary information relating to lines, and grades. These stakes and marks will constitute the field con and in accordance with which the Contractor shall establish necessary controls and perform the work.

The Contractor will be held responsible for the preservation stakes and marks, and if any of the construction stakes or mark been carelessly or willfully destroyed or disturbed by the Cont the cost to the Government of replacing them may be charged a him and may be deducted from the payment for the work.

The Contractor shall notify the Engineer of apparent erro covered in initial stakeout before the affected work is begun. S work be performed in accordance with inaccurate initial stakeout by the Engineer and not discovered by the Contractor, payme such work and any directed correction thereof will be made at a ble unit prices of the contract unless such work differs substa from that described on the plans or in the specifications, in whic the provisions of subsection 109.03 or 109.04 will apply.

105.09 Designation of Engineer. Each project will have a gineer designated as a representative of the Contracting Officer authority in accordance with subsection 105.01. The Contractor notified of the identity of this Engineer before work has begun. 105.10 Duties of the Inspectors. Inspectors are authoriz inspect all work performed and materials furnished, including th paration, fabrication or manufacture of materials to be used; a reject materials and workmanship, or suspend the work, unt questions at issue can be referred to and decided by the Engine Inspectors are not authorized to alter or waive the provisions contract, to issue instructions contrary to the plans and specifica or to act as foreman for the Contractor.

105.11 Inspection of Work.

See SF 23A, General Provisions.

When any unit of government or political subdivision or any ra corporation is to pay a portion of the cost of the work covered b contract, its respective representatives will have the right to in the work. Such inspection will in no sense make such unit of go ment or political subdivision or such railroad corporation a party

contract, and will in no way interfere with the rights of either party hereunder.

105.12 Removal of Unacceptable and Unauthorized Work.

No work shall be performed without lines and grades having been given by the Engineer in accordance with subsection 105.08.

Work done contrary to the instructions of the Engineer, work done beyond the lines shown on the plans, or as given, except as herein specified, or any work done without authority, will be considered as unauthorized and will not be paid for under the provisions of the contract. Work so done may be ordered removed or replaced at the Contractor's expense.

105.13 Load Restrictions. The Contractor shall comply with all legal load restrictions in the hauling of materials on public roads beyond the limits of the project. A special permit will not relieve the Contractor of liability for damage which may result from the moving of material or equipment.

The operation of equipment of such weight or so loaded as to cause damage to structures or the roadway or to any other type of construction will not be permitted. Hauling of materials over the base course or surface course under construction shall be limited as directed. No loads will be permitted on a concrete pavement, base or structure before the expiration of the curing period. Load limits within the project shall not exceed legal limits of adjacent highways unless permitted in writing by the Engineer. The Contractor shall be liable for all damage caused by his hauling equipment.

105.14 Maintenance of the Work During Construction. The Contractor shall maintain the work during construction and until the project is accepted. This maintenance shall be prosecuted as required with adequate equipment and forces to the end that the roadway or structures are kept in satisfactory condition at all times.

All cost of maintenance work during construction and before the project is accepted shall be included in the unit prices bid on the various pay items and the Contractor will not be paid an additional amount for such work except as provided in subsection 104.04.

105.15 Failure to Maintain Roadway or Structure. If the Contractor, at any time, fails to comply with the provisions of subsection 105.14, the Engineer will immediately notify the Contractor of such noncompliance. If the Contractor fails to remedy unsatisfactory maintenance within 24 hours after receipt of such notice the Engineer may immediately proceed to maintain the project, and the entire cost of this maintenance will be deducted from monies due or to become due the Contractor on his contract.

105.16 Acceptance.

(a) Partial Acceptance.-If at any time during the prosecution of the project the Contractor substantially completes a unit or portion of

the project, such as a structure, an interchange, or a section of road or pavement, he may request the Engineer to make final inspection of that unit. If the Engineer finds upon inspection that the unit has been substantially completed in compliance with the contract he may accept that unit as being completed and the Contractor may be relieved of further responsibility for that unit. Such partial acceptance shall in no way void or alter any of the terms of the contract.

(b) Final Acceptance.-Upon due notice from the Contractor of presumptive completion of the entire project, the Engineer will make an inspection. If all construction provided for and contemplated by the contract is found completed in accordance with the contract requirements, that inspection will constitute the final inspection and the Engineer will make the final acceptance and notify the Contractor in writing of this acceptance and of the date after which no further time will be charged.

If, however, the inspection discloses any work, in whole or in part, as being unsatisfactory, the Engineer will so advise the Contractor and the Contractor shall immediately make the necessary corrections.

Upon correction of the work, another inspection will be made which will constitute the final inspection provided the work has been satisfactorily completed. In such event, the Engineer will make the final acceptance and notify the Contractor in writing of this acceptance as provided above.

105.17 Claims for Adjustment and Disputes. See SF 23A, General Provisions

105.18 Automatically Controlled Equipment. Whenever batching or mixing plant equipment is required to be operated automatically under the contract and a breakdown or malfunction of the automatic controls occurs, the equipment may be operated manually or by other methods for a period of 48 hours following the breakdown or malfunction, provided this method of operation will produce results otherwise meeting specifications.

Section 106.-CONTROL OF MATERIAL

106.01 Source of Supply and Quality Requirements.

Unless otherwise provided, all materials used on the work shall be furnished by the Contractor from sources of his choice, except for Borrow, Case 1, which shall be obtained in accordance with subsection 203.03 (1). In order to expedite the inspection and testing of materials, the Contractor shall notify the Engineer of his proposed sources of

materials at the earliest date possible. If it is found after trial that sources of supply for previously approved materials do not produce uniform and satisfactory products or if the product from any source proves unacceptable at any time, the Contractor shall furnish materials from other sources.

106.02 Local Material Sources.

Possible sources of local materials may be shown on the plans or described in the special provisions. The quality of material in such deposits will be acceptable in general, but the Contractor shall determine for himself the amount of equipment and work required to produce a material meeting the specifications. It shall be understood that it is not feasible to ascertain from samples the limit for an entire deposit, and that variations shall be considered as usual and are to be expected. The Engineer may order procurement of material from any portion of a deposit and may reject portions of the deposit as unacceptable.

Unless otherwise provided, the Government will acquire and make available to the Contractor the right to take materials from the sources shown on the plans or described under special provisions, together with the right to use such property as may be specified, for plant site, stockpiles and hauling roads.

If the Contractor elects to use material from sources other than those shown on the plans or described in the special provisions, he shall acquire the necessary rights to take materials from the sources and shall bear all costs related thereto including those for development and exploration and any costs which may result from an increase in length of haul. The use of material from such sources will not be permitted until the Engineer determines, from representative samples obtained and tested at the expense of the Contractor, that an adequate amount of satisfactory materials are available in the source. Additional samples may be required of the Contractor for inspection and testing at Government expense, prior to approval of and authorization to use the

source.

If crushed aggregate is produced from local gravel pits, all oversize material encountered therein with diameters of 12 inches (305 mm) or less shall be crushed and used.

When work areas, gravel pits or other than commercially operated borrow pits are located in or adjacent to live streams or other bodies of water, operations at the sites shall be so controlled, both during and after completion of the work, that erosion will be minimized and sediment will not enter streams or other bodies of water. This may require segregating such areas by a dike or other barrier, treatment of pollutants by filtration, a settling basin or other means sufficient to reduce the sediment content to not more than that of the body of water into which it is discharged.

« PreviousContinue »