| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1968 - 922 pages
...an increase or decrease in the cost of, or the time required for, performance of this contract, an equitable adjustment shall be made in the contract...receive and act upon any such claim asserted at any time/prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1959 - 1028 pages
...in writing within 30 days from the date of receipt by the Contractor of the notification of extra or change : Provided, however, That the Contracting Officer,...upon any such claim asserted at any time prior to the date of final settlement of the contract. If the parties fail to agree upon the adjustment to be... | |
| Administrative law - 1979 - 1304 pages
...Government in accordance therewith; (ii) method of shipment or packing; and (iii) place of delivery. If any such change causes an increase or decrease...Where the cost of property made obsolete or excess as a result of a change is included in the Contractor's claim for adjustment, the Contracting Officer... | |
| Administrative law - 1972 - 684 pages
...Government in accordance therewith; (11) method of shipment or packing; and (ill) place of delivery. If any such change causes an increase or decrease...receive and act upon any such claim asserted at any timo prior to final, payment under this contract. Where the cost of property made obsolete or excess... | |
| Administrative law - 1982 - 690 pages
...any such order, an equitable adjustment shall be made in the contract price, or time of performance, or both, and the contract shall be modified in writing...any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning... | |
| Administrative law - 1979 - 1078 pages
...paid to the contractor; and (3) in such other provisions of the contract as may be affected, and the contract shall be modified in writing accordingly....any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning... | |
| Administrative law - 1981 - 524 pages
...delivery schedule, or both, and (hi contract shall be modified in writing accordingly- Any claim by tht Contractor for adjustment under this clause must be...payment under this contract. Where the cost of property mad* obsolete or excess as a result of a change is included in the Contractor's claim for adjustment,... | |
| Administrative law - 1968 - 1348 pages
...the contractor and/or (111) In such other provisions of the contract as may be so affected, and the contract shall be modified in writing accordingly....receive and act upon any such claim asserted at any tune prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute... | |
| Administrative law - 1976 - 864 pages
...accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within thirty (30) days from the date of receipt by the Contractor...Where the cost of property made obsolete or excess as a result of a change Is Included In the Contractor's claim for adjustment, the Contracting Officer... | |
| Administrative law - 1974 - 788 pages
...or both, and the contract shall be modified In writing accordingly. Any claim by the Contractor ior adjustment under this clause must be asserted within...any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning... | |
| |