Code of Federal Regulations: Containing a Codification of Documents of General Applicability and Future Effect as of December 31, 1948, with Ancillaries and IndexDivision of the Federal Register, the National Archives, 1976 - Administrative law |
From inside the book
Results 1-5 of 100
Page 5
... approval of the Administrator of General Services , hereby is designated the authorized rep- resentative of the Secretary of the Treas- ury in hearing , considering , and deter- mining as fully and finally as might the Secretary , all ...
... approval of the Administrator of General Services , hereby is designated the authorized rep- resentative of the Secretary of the Treas- ury in hearing , considering , and deter- mining as fully and finally as might the Secretary , all ...
Page 19
... approval of shop drawings , testing , approval of samples and other functions of a technical na- ture not involving a change in the scope , price , terms , or conditions of the contract or order . Such designation shall be in writing ...
... approval of shop drawings , testing , approval of samples and other functions of a technical na- ture not involving a change in the scope , price , terms , or conditions of the contract or order . Such designation shall be in writing ...
Page 24
... approval by the office as designated in Administration procedures , a qualification requirement may be in- cluded in a specification only when one or more of the following conditions exist : ( a ) The time required for testing after ...
... approval by the office as designated in Administration procedures , a qualification requirement may be in- cluded in a specification only when one or more of the following conditions exist : ( a ) The time required for testing after ...
Page 25
... approval by the Government of a component shall not constitute excus- able delay when a previously qualified component could have been procured in time to meet the end item delivery schedule . ( c ) Procurements involving qualified ...
... approval by the Government of a component shall not constitute excus- able delay when a previously qualified component could have been procured in time to meet the end item delivery schedule . ( c ) Procurements involving qualified ...
Page 26
... approval by the Government of a component shall not constitute excusable delay when a previously qualified component could have been procured in time to meet the end item delivery schedule . Any change in location or ownership of the ...
... approval by the Government of a component shall not constitute excusable delay when a previously qualified component could have been procured in time to meet the end item delivery schedule . Any change in location or ownership of the ...
Other editions - View all
Common terms and phrases
accordance adjustment Administration advance payments agency agreement amended amount appeal applicable appropriate approval Architect-Engineer award Background Patent bids Bureau Buy American Act Chapter claim clause set cluding contract price Contracting Officer Contractor agrees copy Cost Accounting Standards cost or pricing damage delivery Department deviation Disputes DOTPR employees ernment erty estimated cost evaluation exceed Federal Procurement Regulations FEDERAL REGISTER following clause formance furnished Government property Insert the clause labor liquidated damages material ment modification negotiated nonpersonal notice offeror option paragraph performance period pricing data prior procedures procuring activity proposal pursuant quantity quired rates reasonable reimbursement request Schedule Scope of subpart Secretary small business solicitation Special Bank Account specifications Standards suant subcon Subject Invention submitted supplies termination thereof tion tracting Officer tractor U.S. Coast Guard value engineering
Popular passages
Page 229 - Except as otherwise provided in this contract, any dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided by the Contracting Officer, who shall reduce his decision to writing and mail or otherwise furnish a copy thereof to the Contractor.
Page 229 - Secretary or his duly authorized representative for the determination of such appeals shall be final and conclusive unless determined by a court of competent jurisdiction to have been fraudulent, or capricious, or arbitrary, or so grossly erroneous as necessarily to imply bad faith, or not supported by substantial evidence.
Page 337 - Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change : Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may receive and act upon any such claim asserted at any time prior to final Payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled "Disputes.
Page 353 - ... evidence. In connection with any appeal proceeding under this clause, the Contractor shall be afforded an opportunity to be heard and to offer evidence in support of its appeal. Pending final decision of a dispute hereunder, the Contractor shall proceed diligently with the performance of the contract and in accordance with the Contracting Officer's decision. (b) This "Disputes...
Page 353 - Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change: Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may receive and act upon any such claim asserted at any time prior to final payment under this contract.
Page 229 - Disputes" clause does not preclude consideration of law questions in connection with decisions provided for in paragraph (a) above: provided, that nothing in this contract shall be construed as making final the decision of any administrative official, representative, or board on a question of law.
Page 365 - ... means those articles, materials, and supplies, which are to be acquired under this contract for public use; and (iii) a "domestic source end product" means (A) an unmanufactured end product which has been mined or produced in the United States and (B) an end product manufactured in the United States if the cost of the components thereof which are mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components.
Page 373 - Contractor within such one-year period or authorized extension thereof. Upon failure of the Contractor to submit his termination claim within the time allowed, the Contracting Officer may. subject to any review required by the contracting agency's procedures in effect as of the date of execution of this contract, determine, on the basis of information available to him, the amount, if any, due to the Contractor by reason of the termination and shall thereupon pay to the Contractor the amount so determined....
Page 122 - ... beyond the control and without the fault or negligence of the Contractor. If the failure to perform is caused by the default of a subcontractor, and if such default arises out of causes beyond the control of both the Contractor and subcontractor, and without the fault or negligence of either of them, the Contractor shall not be liable for any excess costs for failure to perform, unless the supplies or services to be furnished by the subcontractor were obtainable from other sources in sufficient...
Page 320 - Contractor shall continue the performance of this contract to the extent not terminated under the provisions of this clause. (c) Except with respect to defaults of subcontractors, the Contractor shall not be liable for any excess costs if the failure to perform the contract arises out of causes beyond the control and without the fault or negligence of the Contractor. Such causes may include, but are not restricted to, acts of God or of the public enemy, acts of the Government in either its sovereign...