Page images
PDF
EPUB

CONTRACT CLAUSES AND SOLICITATION PROVISIONS

7-503.8 Approval of Contract.

APPROVAL OF CONTRACT (1953 JAN)

This contract shall be subject to the written approval of the Secretary or his duly authorized representative and shall not be binding until so approved.

(End of clause)

7-503.9 Patents. In accordance with 9–108, insert the following clause.

PATENT RIGHTS (1975 AUG)

(a) For the purpose of determining the rights of the Government and the Contractor in and to inventions, the Contractor agrees to be bound by all provisions of Executive Order 10096, dated 23 January 1950, and any orders, rules, regulations, or the like issued thereunder.

(b) The Contractor shall: (i) make written disclosure promptly to the Contracting Officer of all inventions of the Contractor which are conceived or first actually reduced to practice during the term of this contract, and sign and execute all papers necessary for conveying to the Government the right to which the Government is entitled in accordance with the determination made under the provisions of Executive Order 10096, or (ii) certify to the Contracting Officer that, to the best of the Contractor's knowledge and belief, no inventions have been conceived or first actually reduced to practice during the term of this contract.

(End of clause)

7-503.10 Pricing of Adjustments. Insert the clause in 7-103.26.

7-504 Clauses To Be Used When Applicable.

7-504.1 Military Security Requirements.

(a) Except as provided in (b) below, insert the Military Security Requirements clause in accordance with 7-104.12.

(b) In any cost reimbursement type contract, insert the Military Security Requirements clause in accordance with 7-204.12.

7-504.2 Rights in Data. In accordance with 7-104.9, insert the appropriate clause, or clauses, therein.

7-504.3 Interest. In accordance with E-620, insert the clause in 7-104.39. 7-504.4 Government Property.

(a) Fixed Price Contracts. Insert the appropriate clause or clauses in 7-104.24.

(b) Cost Reimbursement Contracts. Insert the clause in 7-203.21.

7-504.5 Order of Precedence. In accordance with 3-501(b)Sec.C(xxxi), insert the clause in 7-2003.41.

7-504.6 United States Products and Services (Balance of Payments Program). In accordance with Section VI, Part 8, insert the clause in 7-2003.53.

7-504.7 Identification of Expenditures in the United States. In accordance with 6-807, insert the clause in 7-104.58.

7-504.8 Use of Excess and Near Excess Currency. In accordance with 6–1110, insert the clause in 7-104.66.

7-504.9 Production Progress Report. In accordance with 25-202, insert the clause in 7-104.51.

7-504.10 Examination of Records by Comptroller General. In accordance with 7-104.15, insert the clause therein.

7-504.11 Management Systems Requirements. In accordance with 16–827.1, insert the clause in 7-104.50.

7-504.12 Payment of Interest on Contractors' Claims. In accordance with 1-333, insert the clause in 7-104.82.

7-504.12

ARMED SERVICES PROCUREMENT REGULATION

CONTRACT CLAUSES AND SOLICITATION PROVISIONS

7-504.13 Availability of Funds. In accordance with 1-318, insert one of the clauses in 7-104.91.

7-504.14 Term of Performance or Delivery Date. When applicable, a clause in accordance with 7-104.92 may be used.

7-504.15 Preference for United States Flag Air Carriers. In accordance with 1-336.1(b), insert the clause in 7-104.95.

7-504.16 Privacy Act. In accordance with 1-327.1, insert the clause in 7-104.96.

7-504.17 Preference for Domestic Specialty Metals. In accordance with 7-104.93, insert the applicable clause therein.

7-505 Additional Clause. The following clause shall be inserted in personal services contracts in accordance with Departmental procedures when it is desired to cover the subject matter thereof in such contracts.

7-505.1 Alterations in Contract. In accordance with 7-105.1(a), insert the clause therein.

7-505.1

ARMED SERVICES PROCUREMENT REGULATION

CONTRACT CLAUSES AND SOLICITATION PROVISIONS

Part 6-Construction and Architect-Engineer Contracts

7-600 Scope of Part. This Part sets forth uniform contract clauses for use in connection with the procurement of construction (see 18-100) and of architectengineer services for the production and delivery of designs, plans, drawings and specifications, or for supervision and inspection of construction, or both. For format and clauses to be used in a contract for dismantling, demolition or removal of improvements, see 16-404.

7-601 General. As used throughout this Part, the term “construction contract" means any contract (other than a short form construction contract (see 16-401.2 and 16-402.2), a letter contract, a notice of award, or a modification not effecting new procurement) which is for construction as defined in 18-101.1. 7-602 Required Clauses for Fixed-Price Construction Contracts. The following clauses shall be inserted in all fixed-price construction contracts, except as otherwise provided in this Part.

7-602.1 Definitions.

DEFINITIONS (1964 JUN)

(a) The term "Head of the Agency" or "Secretary" as used herein means the Secretary, the Under Secretary, any Assistant Secretary, or any other head or assistant head of the executive or military department or other Federal agency; and the term “his duly authorized representative" means any person or persons or board (other than the Contracting Officer) authorized to act for the head of the agency or the Secretary.

(b) The term "Contracting Officer" as used herein means the person executing this contract on behalf of the Government and includes a duly appointed successor or authorized representative. (End of clause)

Additional definitions may be included provided they are not inconsistent with the foregoing clause or the provisions of this Regulation.

7-602.2 Specifications and Drawings.

SPECIFICATIONS AND DRAWINGS (1964 JUN)

The Contractor shall keep on the work a copy of the drawings and specifications and shall at all times give the Contracting Officer access thereto. Anything mentioned in the specifications and not shown on the drawings, or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned in both. In case of difference between drawings and specifications, the specifications shall govern. In case of discrepancy either in the figures, in the drawings, or in the specifications, the matter shall be promptly submitted to the Contracting Officer, who shall promptly make a determination in writing. Any adjustment by the Contractor without such a determination shall be at his own risk and expense. The Contracting Officer shall furnish from time to time such detail drawings and other information as he may consider necessary, unless otherwise provided.

(End of clause)

7-602.3 Changes.

CHANGES (1968 FEB)

(a) The Contracting Officer may, at any time, without notice to the sureties, by written order designated or indicated to be a change order, make any change in the work within the general scope of the contract, including but not limited to changes:

7-602.3

ARMED SERVICES PROCUREMENT REGULATION

CONTRACT CLAUSES AND SOLICITATION PROVISIONS

(i) in the specifications (including drawings and designs);

(ii) in the method or manner of performance of the work;

(iii) in the Government-furnished facilities, equipment, materials, services, or site; or

(iv) directing acceleration in the performance of the work.

(b) Any other written order or an oral order (which terms as used in this paragraph (b) shall include direction, instruction, interpretation or determination) from the Contracting Officer, which causes any such change, shall be treated as a change order under this clause, provided that the Contractor gives the Contracting Officer written notice stating the date, circumstances, and source of the order and that the Contractor regards the order as a change order.

(c) Except as herein provided, no order, statement, or conduct of the Contracting Officer shall be treated as a change under this clause or entitle the Contractor to an equitable adjustment hereunder.

(d) If any change under this clause causes an increase or decrease in the Contractor's cost of, or the time required for, the performance of any part of the work under this contract, whether or not changed by any order, an equitable adjustment shall be made and the contract modified in writing accordingly: Provided, however, That except for claims based on defective specifications, no claim for any change under (b) above shall be allowed for any costs incurred more than 20 days before the Contractor gives written notice as therein required: And provided further, That in the case of defective specifications for which the Government is responsible, the equitable adjustment shall include any increased cost reasonably incurred by the Contractor in attempting to comply with such defective specifications.

(e) If the Contractor intends to assert a claim for an equitable adjustment under this clause, he must, within 30 days after receipt of a written change order under (a) above or the furnishing of a written notice under (b) above, submit to the Contracting Officer a written statement setting forth the general nature and monetary extent of such claim, unless this period is extended by the Government. The statement of claim hereunder may be included in the notice under (b) above. (f) No claim by the Contractor for an equitable adjustment hereunder shall be allowed if asserted after final payment under this contract.

(End of clause)

In the foregoing clause, the period of "30 days" within which any claim for adjustment must be asserted may be varied in accordance with Departmental procedures. In accordance with 10 U.S.C. 2306(f), prior to the pricing of any change order that is expected to exceed $100,000, except where the price is based on adequate price competition, established catalog or market prices of commercial items sold in substantial quantities to the general public, or prices set by law or regulation, the contracting officer shall require the contractor to furnish a Certificate of Current Cost or Pricing Data (see 3-807.4) and shall assure that the contract includes or is modified to include a defective pricing data clause (see 7-104.29).

7-602.4 Differing Site Conditions.

DIFFERING SITE CONDITIONS (1968 FEB)

(a) The Contractor shall promptly, and before such conditions are disturbed, notify the Contracting Officer in writing of: (1) subsurface or latent physical conditions at the site differing materially from those indicated in this contract, or (2) unknown physical conditions at the site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in this contract. The Contracting Officer shall promptly investigate the conditions, and if he finds that such conditions do materially so differ and cause an increase or decrease in the Contractor's cost of, or the time required for, performance of any part of the work under this contract, whether or not changed as a result of such conditions, an equitable adjustment shall be made and the contract modified in writing accordingly.

7-602.4

ARMED SERVICES PROCUREMENT REGULATION

CONTRACT CLAUSES AND SOLICITATION PROVISIONS

(b) No claim of the Contractor under this clause shall be allowed unless the Contractor has given the notice required in (a) above; provided, however, the time prescribed therefor may be extended by the Government.

(c) No claim by the Contractor for an equitable adjustment hereunder shall be allowed if asserted after final payment under this contract.

(End of clause)

In accordance with 10 U.S.C. 2306(f), prior to the pricing of any modification pursuant to the “Differing Site Conditions" clause that is expected to exceed $100,000, except where the price is based on adequate price competition, established catalog or market prices of commercial items sold in substantial quantities to the general public, or prices set by law or regulation, the contracting officer shall require the contractor to furnish a Certificate of Current Cost or Pricing Data (see 3-807.4) and shall assure that the contract includes or is modified to include a defective pricing data clause (see 7-104.29).

7-602.5 Termination for Default—Damages for Delay-Time Extensions. In accordance with 8–709, insert the following clause.

TERMINATION FOR DEFAULT-DAMAGES FOR DELAY-TIME EXTENSIONS (1969

AUG)

(a) If the Contractor refuses or fails to prosecute the work, or any separable part thereof, with such diligence as will insure its completion within the time specified in this contract, or any extension thereof, or fails to complete said work within such time, the Government may, by written notice to the Contractor, terminate his right to proceed with the work or such part of the work as to which there has been delay. In such event the Government may take over the work and prosecute the same to completion, by contract or otherwise, and may take possession of and utilize in completing the work such materials, appliances, and plant as may be on the site of the work and necessary therefor. Whether or not the Contractor's right to proceed with the work is terminated, he and his sureties shall be liable for any damage to the Government resulting from his refusal or failure to complete the work within the specified time.

(b) If fixed and agreed liquidated damages are provided in the contract and if the Government so terminates the Contractor's right to proceed, the resulting damage will consist of such liquidated damages until such reasonable time as may be required for final completion of the work together with any increased costs occasioned the Government in completing the work.

(c) If fixed and agreed liquidated damages are provided in the contract and if the Government does not so terminate the Contractor's right to proceed, the resulting damage will consist of such liquidated damages until the work is completed or accepted.

(d) The Contractor's right to proceed shall not be so terminated nor the Contractor charged with resulting damage if:

(1) The delay in the completion of the work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to, acts of God, acts of the public enemy, acts of the Government in either its sovereign or contractual capacity, acts of another Contractor in the performance of a contract with the Government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, unusually severe weather, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of both the Contractor and such subcontractors or suppliers; and

(2) The Contractor, within 10 days from the beginning of any such delay (unless the Contracting Officer grants a further period of time before the date of final payment under the contract), notifies the Contracting Officer in writing of the causes of delay. The Contracting Officer shall ascertain the facts and the extent of the delay and extend the time for completing the work when, in his judgment, the findings of fact justify such an extension, and his findings of fact shall be final and conclusive on the parties, subject only to appeal as provided in the “Disputes" clause of this contract.

7-602.5

ARMED SERVICES PROCUREMENT REGULATION

« PreviousContinue »