| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1959 - 1028 pages
...Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may receive, and act upon any such claim asserted at any time prior to the date of final settlement of the contract. If the parties fail to agree upon the adjustment to be... | |
| United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1962 - 712 pages
...two-year period or authorized extension thereof. However, if the Contracting Officer determines that the facts justify such action, he may receive and act upon any such termination claim at any time after such two-year period or any extension thereof. Upon failure of... | |
| Administrative law - 1975 - 1236 pages
...any part of this contract, and (ii) the Contractor asserts a claim for such adjustment within thirty (30) days after the end of the period of work stoppage;...under this contract. (c) If a stop work order is not canceled and the work covered by such order is terminated for the convenience of the Government, the... | |
| Administrative law - 1976 - 1202 pages
...any part of this contract; and (ii) the Contractor asserts a claim for such adjustment within thirty (30) days after the end of the period of work stoppage;...prior to final payment under this contract. (c) If a Slop Work Order is not canceled and the work covered by such order is terminated, the reasonable costs... | |
| Administrative law - 1974 - 686 pages
...any part of this contract; and (i1) The Contractor asserts a claim for such adjustment within thirty (30) days after the end of the period of work stoppage;...any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning... | |
| Administrative law - 1981 - 706 pages
...any part of this contract, and (2) The contractor asserts a claim for such adjustment within thirty (30) days after the end of the period of work stoppage;...any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning... | |
| Administrative law - 1970 - 788 pages
...any pan of this contract, and (11) the Contractor asserts a claim for such adjustment within thirty (30) days after the end of the period of work stoppage...receive and act upon any such claim asserted at any tune prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute... | |
| Administrative law - 1974 - 640 pages
...any part of this contract; and (II) The Contractor asserts a claim for such adjustment within thirty (30) days after the end of the period of work stoppage;...receive and act upon any such claim asserted at any tune prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute... | |
| Administrative law - 1977 - 722 pages
...the contractor's cost properly allocable to, the performance of any part of this contract, and (ii) the contractor asserts a claim for such adjustments...officer decides the facts justify such action, he nay receive and act upon any such claim asserted at any time prior to final payment under this contract.... | |
| Administrative law - 1970 - 260 pages
...and made to the contracting officer within thirty (30) days after the termination of such suspension: Provided, That if the contracting officer decides...any time prior to final payment under this contract. Failure to agree to any adjustment shall be a dispute concerning a question of fact within the meaning... | |
| |