The School Executive's Guide to Performance Contracting |
From inside the book
Results 1-5 of 17
Page
... amount ; however , if local funds are used , local authorities will have to an- swer this question . 3. Do RFP specifications adequately consider turnkey requirements ? Assume that federal funds ( e.g. , Title I , ESEA ) are available ...
... amount ; however , if local funds are used , local authorities will have to an- swer this question . 3. Do RFP specifications adequately consider turnkey requirements ? Assume that federal funds ( e.g. , Title I , ESEA ) are available ...
Page 4
... amount . Total Suggested payment schedule with rationale for same . Contract ( s ) award ( s ) will be made to the institution whose proposal is most advantageous to the Dallas In- dependent School District . The Dallas Independent ...
... amount . Total Suggested payment schedule with rationale for same . Contract ( s ) award ( s ) will be made to the institution whose proposal is most advantageous to the Dallas In- dependent School District . The Dallas Independent ...
Page 8
... amount of effort in training local personnel employed by the Dallas Independent School District in the maintenance and servicing of said equipment , upon request of the Project Director . 62 8/13/70 Contractor agrees during each week of ...
... amount of effort in training local personnel employed by the Dallas Independent School District in the maintenance and servicing of said equipment , upon request of the Project Director . 62 8/13/70 Contractor agrees during each week of ...
Page 15
... amount of $ 10,000.00 or more ( $ 20,000.00 or more if solely for standard commer- cial supplies or raw materials ) , the Contractor shall , within twenty ( 20 ) days after award of such subcontract or purchase order , advise the ...
... amount of $ 10,000.00 or more ( $ 20,000.00 or more if solely for standard commer- cial supplies or raw materials ) , the Contractor shall , within twenty ( 20 ) days after award of such subcontract or purchase order , advise the ...
Page 16
... amount of $ 27,083 . for startup cost within seven ( 7 ) days from the effective date of operations . Thereafter , the con- tractor will submit ten equal invoices in the amount of $ 18,164 . at the end of each month . The above billings ...
... amount of $ 27,083 . for startup cost within seven ( 7 ) days from the effective date of operations . Thereafter , the con- tractor will submit ten equal invoices in the amount of $ 18,164 . at the end of each month . The above billings ...
Other editions - View all
Common terms and phrases
1817 LIBRARIES Accelerated Learning Achievement Achievement Motivation and/or assessment Auditing Contractor August 13 Banneker basis Blaschke Central Daylight Century agrees Century's classroom Communications and Mathematics Contractor agrees cost effectiveness criterion-referenced tests Dallas Independent School decision determine documents Education Audit Group equipment evaluation funds grade level Grand Rapids GUARANTEED STUDENT PERFORMANCE Independent School District instructional system interim performance test interim test Junior High Learning Achievement Centers Management Support Group mance Mathematics programs measure Mecklenburger Meredith Corporation munications and Mathematics objectives operations payment percent PERFORMANCE IN EDUCATION personnel Phi Delta Kappan planning post-test procedures Project Administrator Project Director Project Manager Rand Rand Corporation Reading Communications reimbursement reports Request for Proposal responsible schedule school board school system scores specific staff student achievement student dropouts subcontractor submit teachers Texarkana Thiokol Chemical Corporation Thiokol Corporation thirty 30 tract tractor unit price UNIV
Popular passages
Page 21 - Except as otherwise provided in this contract, any dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided...
Page 21 - Such causes may include, but are not restricted to, acts of God or of the public enemy, acts of the Government m either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather...
Page 23 - Contractor shall not be liable for any excess costs if the failure to perform the contract arises out of causes beyond the control and without the fault or negligence of the Contractor. Such causes may include, but are not restricted to, acts of God or of the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather...
Page 22 - The decision of the Secretary or his duly authorized representative for the determination of such appeals shall be final and conclusive unless determined by a court of competent Jurisdiction to have been fraudulent, or capricious, or arbitrary, or so grossly erroneous as necessarily to imply bad faith, or not supported by substantial evidence.
Page 22 - ... agencies maintained by the Contractor for the purpose of securing business. For breach or violation of this warranty the Government shall have the right to annul this contract without liability, or In Its discretion to deduct from the contract price or consideration, or otherwise recover, the full amount of such commission, percentage, brokerage, or contingent fee.
Page 23 - Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather; but in every case the failure to perform must be beyond the control and without the fault or negligence of the Contractor.
Page 20 - The Government, through any authorized representatives, has the right, at all reasonable times, to Inspect, or otherwise evaluate the work performed or being performed hereunder and the premises in which it is being performed. If any Inspection, or evaluation Is made by the Government on the premises of the Contractor or a subcontractor, the Contractor shall provide and shall require...
Page 21 - Except with respect to defaults of subcontractors, the Contractor shall not be in default by reason of any failure in performance of this contract In accordance with its terms (including any failure by the Contractor to make progress in the prosecution of the work hereunder which endangers such performance) If such failure arises out of causes beyond the control and without the fault or negligence of the Contractor. Such causes may Include, but are not restricted to: Acts...
Page 21 - ... is one of a number of subcontracts under this contract with a single subcontractor for the same or related supplies or services which, in the aggregate are expected to exceed $100,000 ; the advance notification required by (a) above shall include...
Page 20 - ... records") to the extent and in such detail as will properly reflect all net costs, direct and indirect, of labor, materials, equipment, supplies and services, and other costs and expenses of whatever nature for which reimbursement is claimed under the provisions of this contract.