Expenditures and Obligations to date, under $30,600,000 appropriated for project Expenditures and obligations have been incurred to September 30, 1978 as follows: Consulting Engineering Services. Contract for the manufacture, delivery, and installation of $ 1,334,099 4 large centrifugal refrigeration machines having a total refrigeration capacity of 24,000 tons, including 4 pumpdown units and refrigeration receivers. 2,312,468 Contract for site preparation work for a new 24,000-ton Refrigeration Plant Building. 1,329,185 Contract for New Refrigeration Building, Operations Building, and North header tunnel. 5,719,965 Contracts for furnishing and delivering of structural steel, valves, piping system components, and chilled water and condensor pumps for the new Refrigeration Plant..... 2,556,548 Mechanical, Electrical and other related work. Administration, blueprints, tests, surveys, central control systems, and other miscellaneous items.. Total Expended and Obligated to 9/30/78. Unobligated Balance, 9/30/78, of $30,600,000 appropriated for project Expended and obligated to 9/30/78. Total appropriated for project.. Unobligated balance, available as of 9/30/78. Obligations remaining to be incurred Work remaining to complete the project, in accordance with the Authorization Act, as well as a with the following projected schedule: Phase I Work under this Phase includes the following contracts: - Manufacture, delivery, and installation of 4 large centrifugal refrigeration machines having a total capacity of 24,000 tons, and 4 pump-down units and refrigeration receivers Contract awarded December 11, 1973; anticipated completion date for all acceptance. work under contract, June 1979, except final testing and Manufacture, delivery, and installation of a cooling tower Contract awarded March 21, 1974; anticipated completion date except final testing and acceptance. for all work under contract, including installation, June 1979, 1.10 April 4, 1974; all work under contract now substantially completed. Fabrication and delivery of structural steel for new Refrigeration Plant Building Contract awarded December 2, 1974; all work under contract now completed. Piping system components for new Refrigeration Plant Contract awarded December 27, 1974; all work under contract now completed. Electric motor-operated ball valves for new Refrigeration Contract awarded March 13, 1975; all work under Plant 11 Site preparation work for a new 24,000 ton Refrigeration Plant Building Contract awarded July 10, 1974; all work under contract is now completed. 1.11 Construction of a new building to house a refrigeration plant of 24,000-ton capacity; construction of a new operations building for centralization and administration of control functions of both the new and existing refrigeration plants; installation of a tunnel across the north portion of the existing power plant site, for subsequent installation therein (under a separate contract) of a new underground chilled water "headering" system Contract awarded May 20, 1976; all work under contract now substantially completed. Phase IV - Procurement and installation of mechanical and electrical equipment in new Phase V Procurement of dust collectors, central control systems for new operations Projected completion date of all work under project December 1980. 1.12 This project was authorized by Public Law 92-607, approved October 31, 1972, "Supplemental The 1973 Authorization Act was amended by Public Law 93-245, approved January 3, 1974, In summary, the total authorized and appropriated for the project to date, amounts to The following statements show the status of work, phasing of work, and projected time schedule under the project. Status of Work under Project Work under this project is progressing satisfactorily. The work, as the Committee has been Competitive bids for Phase III were invited for the exterior stone for the Dirksen Building |