(c) Content. A DOE EA shall comply with the requirements found at 40 CFR 1508.9. In addition to any other alternatives, DOE shall assess the no action alternative in an EA, even when the proposed action is specifically required by legislation or a court order.

§ 1021.322 Findings of no significant impact.

(a) DOE shall prepare a FONSI only if the related EA supports the finding that the proposed action will not have a significant effect on the human environment. If a required DOE EA does not support a FONSI, DOE shall prepare an EIS and issue a ROD before taking action on the proposal addressed by the EA, except as permitted under 40 CFR 1506.1 and § 1021.211 of this part.

(b) In addition to the requirements found at 40 CFR 1508.13, a DOE FONSI shall include the following:

(1) Any commitments to mitigations that are essential to render the impacts of the proposed action not significant, beyond those mitigations that are integral elements of the proposed action, and a reference to the Mitigation Action Plan prepared under §1021.331 of this part;

(2) Any "Statement of Findings" required by 10 CFR part 1022, "Compliance with Floodplain/Wetlands Environmental Review Requirements";

(3) The date of issuance; and

(4) The signature of the DOE approving official.

(c) DOE shall make FONSIS available to the public as provided at 40 CFR 1501.4(e)(1) and 1506.6; DOE shall make copies available for inspection in the appropriate DOE public reading room(s) or other appropriate location(s) for a reasonable time.

(d) DOE shall issue a proposed FONSI for public review and comment before making a final determination on the FONSI if required by 40 CFR 1501.4(e)(2); DOE may issue a proposed FONSI for public review and comment in other situations as well.

(e) Upon issuance of the FONSI, DOE may proceed with the proposed action subject to any mitigation commitments expressed in the FONSI that are essential to render the impacts of the proposed action not significant.

(f) DOE may revise a FONSI at any time, so long as the revision is supported by an existing EA. A revised FONSI is subject to all provisions of paragraph (d) of this section.

[57 FR 15144, Apr. 24, 1992, as amended at 61 FR 36239, July 9, 1996]

§ 1021.330 Programmatic (including site-wide) NEPA documents.

(a) When required to support a DOE programmatic decision (40 CFR 1508.18(b)(3)), DOE shall prepare a programmatic EIS or EA (40 CFR 1502.4). DOE may also prepare a programmatic EIS or EA at any time to further the purposes of NEPA.

(b) A DOE programmatic NEPA document shall be prepared, issued, and circulated in accordance with the requirements for any other NEPA document, as established by the CEQ Regulations and this part.

(c) As a matter of policy when not otherwise required, DOE shall prepare site-wide EISS for certain large, multiple-facility DOE sites; DOE may prepare EISS or EAS for other sites to assess the impacts of all or selected functions at those sites.

(d) DOE shall evaluate site wide NEPA documents prepared under §1021.330(c) at least every five years. DOE shall evaluate site-wide EISS by means of a Supplement Analysis, as provided in § 1021.314. Based on the Supplement Analysis, DOE shall determine whether the existing EIS remains adequate or whether to prepare a new sitewide EIS or supplement the existing EIS, as appropriate. The determination and supporting analysis shall be made available in the appropriate DOE public reading room(s) or in other appropriate location(s) for a reasonable time.

(e) DOE shall evaluate site-wide EAS by means of an analysis similar to the Supplement Analysis to determine whether the existing site-wide EA remains adequate, whether to prepare a new site-wide EA, revise the FONSI, or prepare a site wide EIS, as appropriate. The determination and supporting analysis shall be made available in the appropriate DOE public reading room(s) or in other appropriate location(s) for a reasonable time.

§ 1021.331 Mitigation action plans.

(a) Following completion of each EIS and its associated ROD, DOE shall prepare a Mitigation Action Plan that addresses mitigation commitments expressed in the ROD. The Mitigation Action Plan shall explain how the corresponding mitigation measures, designed to mitigate adverse environmental impacts associated with the course of action directed by the ROD, will be planned and implemented. The Mitigation Action Plan shall be prepared before DOE takes any action directed by the ROD that is the subject of a mitigation commitment.

(b) In certain circumstances, as specified in §1021.322(b)(2), DOE shall also prepare a Mitigation Action Plan for commitments to mitigations that are essential to render the impacts of the proposed action not significant. The Mitigation Action Plan shall address all commitments to such necessary mitigations and explain how mitigation will be planned and implemented. The Mitigation Action Plan shall be prepared before the FONSI is issued and shall be referenced therein.

(c) Each Mitigation Action Plan shall be as complete as possible, commensurate with the information available regarding the course of action either directed by the ROD or the action to be covered by the FONSI, as appropriate. DOE may revise the Plan as more specific and detailed information becomes available.

(d) DOE shall make copies of the Mitigation Action Plans available for inspection in the appropriate DOE public reading room(s) or other appropriate location(s) for a reasonable time. Copies of the Mitigation Action Plans shall also be available upon written request.

§ 1021.340 Classified, confidential, and otherwise exempt information.

(a) Notwithstanding other sections of this part, DOE shall not disclose classified, confidential, or other information that DOE otherwise would not disclose pursuant to the Freedom of Information Act (FOIA) (5 U.S.C. 552) and 10 CFR 1004.10(b) of DOE's regulations implementing the FOIA, except as provided by 40 CFR 1506.6(f).

(b) To the fullest extent possible. DOE shall segregate any information that is exempt from disclosure requirements into an appendix to allow public review of the remainder of a NEPA document.

(c) If exempt information cannot be segregated, or if segregation would leave essentially meaningless material, DOE shall withhold the entire NEPA document from the public; however, DOE shall prepare the NEPA document, in accordance with the CEQ Regulations and this part, and use it in DOE decisionmaking.

§ 1021.341 Coordination with other environmental review requirements.

(a) In accordance with 40 CFR 1500.4(k) and (o), 1502.25. and 1506.4. DOE shall integrate the NEPA process and coordinate NEPA compliance with other environmental review requirements to the fullest extent possible.

(b) To the extent possible, DOE shall determine the applicability of other environmental requirements early in the planning process, in consultation with other agencies when necessary or appropriate, to ensure compliance and to avoid delays, and shall incorporate any relevant requirements as early in the NEPA review process as possible.

§ 1021.342 Interagency cooperation.

For DOE programs that involve another Federal agency or agencies in related decisions subject to NEPA, DOE will comply with the requirements of 40 CFR 1501.5 and 1501.6. As part of this process, DOE shall cooperate with the other agencies in developing environmental information and in determining whether a proposal requires preparation of an EIS or EA, or can be categorically excluded from preparation of either. Further, where appropriate and acceptable to the other agencies, DOE shall develop or cooperate in the development of interagency agreements to facilitate coordination and to reduce delay and duplication.

§ 1021.343 Variances.

(a) Emergency actions. DOE may take an action without observing all provisions of this part or the CEQ Regulations, in accordance with 40 CFR 1506.11, in emergency situations that

demand immediate action. DOE shall consult with CEQ as soon as possible regarding alternative arrangements for emergency actions having significant environmental impacts. DOE shall document, including publishing a notice in the FEDERAL REGISTER, emergency actions covered by this paragraph within 30 days after such action occurs; this documentation shall identify any adverse impacts from the actions taken, further mitigation necessary, and any NEPA documents that may be required.

(b) Reduction of time periods. On a case-by-case basis, DOE may reduce time periods established in this part that are not required by the CEQ Regulations. If DOE determines that such reduction is necessary, DOE shall publish a notice in the FEDERAL REGISTER specifying the revised time periods and the rationale for the reduction.

(c) Other. Any variance from the requirements of this part, other than as provided by paragraphs (a) and (b) of this section, must be soundly based on the interests of national security or the public health, safety, or welfare and must have the advance written approval of the Secretary; however, the Secretary is not authorized to waive or grant a variance from any requirement of the CEQ Regulations (except as provided for in those regulations). If the Secretary determines that a variance from the requirements of this part is within his/her authority to grant and is necessary, DOE shall publish a notice in the FEDERAL REGISTER specifying the variance granted and the reasons.

Subpart D-Typical Classes of Actions

§ 1021.400 Level of NEPA review.

(a) This subpart identifies DOE actions that normally:

(1) Do not require preparation of either an EIS or an EA (are categorically excluded from preparation of either document) (appendices A and B to this subpart D);

(2) Require preparation of an EA, but not necessarily an EIS (appendix C to this subpart D); or

(3) Require preparation of an EIS (appendix D to this subpart D).

(b) Any completed, valid NEPA review does not have to be repeated, and no completed NEPA documents need to be redone by reasons of these regulations, except as provided in § 1021.314.

(c) If a DOE proposal is encompassed within a class of actions listed in the appendices to this subpart D, DOE shall proceed with the level of NEPA review indicated for that class of actions, unless there are extraordinary circumstances related to the specific proposal that may affect the significance of the environmental effects of the proposal.

(d) If a DOE proposal is not encompassed within the classes of actions listed in the appendices to this subpart D, or if there are extraordinary circumstances related to the proposal that may affect the significance of the environmental effects of the proposal, DOE shall either:

(1) Prepare an EA and, on the basis of that EA, determine whether to prepare an EIS or a FONSI; or

(2) Prepare an EIS and ROD.

§ 1021.410 Application of categorical exclusions (classes of actions that normally do not require EAs or EISS).

(a) The actions listed in appendices A and B to this subpart D are classes of actions that DOE has determined do not individually or cumulatively have a significant effect on the human environment (categorical exclusions).

(b) To find that a proposal is categorically excluded, DOE shall determine the following:

(1) The proposal fits within a class of actions that is listed in appendix A or B to this subpart D;

(2) There are no extraordinary circumstances related to the proposal that may affect the significance of the environmental effects of the proposal. Extraordinary circumstances are unique situations presented by specific proposals, such as scientific controversy about the environmental effects of the proposal; uncertain effects or effects involving unique or unknown risks; or unresolved conflicts concerning alternate uses of available resources within the meaning of section 102(2)(E) of NEPA; and

(3) The proposal is not "connected" (40 CFR 1508.25(a)(1)) to other actions with potentially significant impacts, is not related to other proposed actions with cumulatively significant impacts (40 CFR 1508.25(a)(2)), and is not precluded by 40 CFR 1506.1 or §1021.211 of this part.

(c) All categorical exclusions may be applied by any organizational element of DOE. The sectional divisions in appendix B to this subpart D are solely for purposes of organization of that appendix and are not intended to be limiting.

(d) A class of actions includes activities foreseeably necessary to proposals encompassed within the class of actions (such as associated transportation activities and award of implementing grants and contracts).

[blocks in formation]

amend

A2 Contract interpretations, ments, and modifications that are clarifying or administrative in nature.

A3 Adjustments, exceptions, exemptions, appeals, and stays, modifications, or rescissions of orders issued by the Office of Hearings and Appeals.

A4 Interpretations and rulings with respect to existing regulations, or modifications or rescissions of such interpretations and rulings.

A5 Rulemaking interpreting or amending an existing rule or regulation that does not change the environmental effect of the rule or regulation being amended.

A6 Rulemakings that are strictly procedural, such as rulemaking (under 48 CFR part 9) establishing procedures for technical and pricing proposals and establishing contract clauses and contracting practices for the purchase of goods and services, and rulemaking (under 10 CFR part 600) establishing application and review procedures for, and administration, audit, and closeout of, grants and cooperative agreements.

A7 Transfer, lease, disposition, or acquisition of interests in personal property (e.g.. equipment and materials) or real property (e.g., permanent structures and land), if property use is to remain unchanged; i.e.. the type and magnitude of impacts would remain essentially the same.

A8 Award of contracts for technical sup port services, management and operation of a government-owned facility, and personal services.

A9 Information gathering (including, but not limited to, literature surveys, inventories, audits), data analysis (including computer modelling), document preparation (such as conceptual design or feasibility studies, analytical energy supply and demand studies), and dissemination (including, but not limited to, document mailings, publication, and distribution; and classroom training and informational programs), but not including site characterization or environmental monitoring. (Also see B3.1.)

A10 Reports or recommendations on legislation or rulemaking that is not proposed by DOE.

All Technical advice and planning assistance to international, national, state, and local organizations.

A12 Emergency preparedness planning activities, including the designation of onsite evacuation routes.

A13 Administrative, organizational, or procedural Orders, Notices, and guidelines.

A14 Approval of technical exchange ar rangements for information, data, or personnel with other countries or international organizations, including, but not limited to, assistance in identifying and analyzing another country's energy resources, needs and options.

[blocks in formation]

B1.2 B1.3

Training exercises and simulation Routine maintenance/custodial services for buildings, structures, infrastructures, equipment

B1.4 Installation/modification of air conditioning systems for existing equipment B1.5 Improvements to cooling water systems within existing building, structure B1.6 Installation/modification of retention tanks, small basins to control runoff, spills

B1.7 Acquisition/installation/operation/re

moval of communication systems, data processing equipment

B1.8 Modifications to screened water intake/outflow structures

B1.9 Placement of airway safety markings/ painting (not lighting) of existing lines, antennas

B1.10 Routine onsite storage of activated material at existing facility

B1.11 Fencing, no adverse effect on wildlife movement/surface water flow

B1.12 Detonation/burning of failed/damaged high explosives or propellants

B1.13 Construction/acquisition/relocation of onsite pathways, short onsite roads/railroads

B1.14

access

Refueling of a nuclear reactor B1.15 Siting/construction/operation of support buildings/support structures

B1.16 Removal of asbestos from buildings B1.17 Removal of polychlorinated biphenylcontaining items from buildings, other aboveground locations

B1.18 Siting/construction/operation of additional/replacement water supply wells

B1.19 Siting/construction/operation

of

[blocks in formation]
[blocks in formation]

B3.6 Siting/construction/operation/decom

missioning of facilities for bench-scale research, conventional laboratory operations, small-scale research and development and pilot projects

B3.7 Siting/construction/operation of new infill exploratory, experimental oil/gas/ geothermal wells

B3.8 Outdoor ecological/environmental research in small area

B3.9 Certain Clean Coal Technology Demonstration Program activities B3.10 Siting/construction/operation/decommissioning of particle accelerators, including electron beam accelerators, primary beam energy less than approximately 100 MeV