Department of Defense appropriations for 1982: hearings before a subcommittee of the Committee on Appropriations, House of Representatives, Ninety-seventh Congress, first session ....U.S. Government Printing Office, 1981 - United States |
From inside the book
Results 1-5 of 83
Page 64
... tanks revealed some deterioration of the epoxy paint coating . In December , 1980 , Electric Boat requested a waiver to defer final painting until the first drydocking after delivery for the following reasons : ( 1 ) epoxy painting in ...
... tanks revealed some deterioration of the epoxy paint coating . In December , 1980 , Electric Boat requested a waiver to defer final painting until the first drydocking after delivery for the following reasons : ( 1 ) epoxy painting in ...
Page 74
... tanks . You can use the concept there . But when you procure ships which cost several hundred million dollars , or a billion dollars per unit , you cannot readily do that . Mr. WHITTEN . Don't misunderstand me . Your contract has to be ...
... tanks . You can use the concept there . But when you procure ships which cost several hundred million dollars , or a billion dollars per unit , you cannot readily do that . Mr. WHITTEN . Don't misunderstand me . Your contract has to be ...
Page 189
... tank top , it would have included the counterbored hole added by the proposed drawing revision ... " . 5 . " Although Electric Boat has withdrawn its notification , it is important to point out , in the interest of avoiding future ...
... tank top , it would have included the counterbored hole added by the proposed drawing revision ... " . 5 . " Although Electric Boat has withdrawn its notification , it is important to point out , in the interest of avoiding future ...
Page 233
... tanks ( M - 60 and XM - 1 ) and many types of munitions . 8. The concept of Government - owned , contractor - operated shipyards is not a panacea for the present shipbuilding contract problems -- but neither is a resolution which would ...
... tanks ( M - 60 and XM - 1 ) and many types of munitions . 8. The concept of Government - owned , contractor - operated shipyards is not a panacea for the present shipbuilding contract problems -- but neither is a resolution which would ...
Page 359
... TANK AUTOMOTIVE COMMAND INTRODUCTION Mr. ADDABBO . The committee will come to order . The committee will consider today the Army's program to develop and procure a High Mobility Multi - Purpose Wheeled Vehicle , the so - called HMMWV ...
... TANK AUTOMOTIVE COMMAND INTRODUCTION Mr. ADDABBO . The committee will come to order . The committee will consider today the Army's program to develop and procure a High Mobility Multi - Purpose Wheeled Vehicle , the so - called HMMWV ...
Other editions - View all
Common terms and phrases
acquisition ADDABBO Admiral HOLCOMB Admiral RICKOVER aircraft armor Army ASBCA award basis budget cancellation ceiling capability Chairman CHAPPELL Chief of Naval claims lawyers Claims Settlement clause combat Committee Congress construction contract changes contract disputes Contract Law Section contractor cost CUCV decision Defense Department DELAUER Department of Defense diesel engine dollars drawing revisions Dynamics EDWARDS Electric Boat equipment fiscal year 1982 full funding Gama Goat going Government helicopter HMMWV inflated issue KEITH Litton memorandum ment million missile mobility multiyear contracting multiyear procurement MURTHA Naval Sea Systems NAVSEA Navy's Newport nuclear Office Operations percent Pershing II problems production proposed Public Contract Law question recommendations request requirements Sea Systems Command Secretary of Defense Ship Procurement shipbuilding claims shipbuilding contracts shipyard SKIBBIE Soviet SSN 688 Class submarines submitted TACFIRE tank target TRIDENT vehicles weapon systems
Popular passages
Page 195 - The decision of the Secretary or his duly authorized representative for the determination of such appeals shall be final and conclusive unless determined by a court of competent jurisdiction to have been fraudulent, or capricious, or arbitrary, or so grossly erroneous as necessarily to imply bad faith, or not supported by substantial evidence.
Page 195 - Disputes" clause does not preclude consideration of law questions in connection with decisions provided for in paragraph (a) above: Provided, That nothing in this contract shall be construed as making final the decision of any administrative official, representative, or board on a question of law.
Page 210 - If it looks like a duck, walks like a duck and quacks like a duck, it's a duck.
Page 38 - WE SHALL BUILD GOOD SHIPS HERE "AT A PROFIT - IF WE CAN "AT A LOSS - IF WE MUST "BUT ALWAYS GOOD SHIPS" WHEN TENNECO TOOK OVER THE YARD, COMPANY OFFICIALS REMOVED THE PLAQUE AND SHIPPED IT OFF TO A LOCAL MUSEUM.
Page 181 - Fraud, indeed, in the sense of a court of equity properly includes all acts, omissions and concealments which involve a breach of legal or equitable duty, trust, or confidence, justly reposed, and are injurious to another, or by which an undue and unconscientious advantage is taken of another.
Page 779 - ... Government. If award is made on the multiyear basis, funds are obligated only for the first year's quantity, with succeeding years' contract quantities funded annually thereafter. In the event funds are not made available to support one or more succeeding year's quantities, cancellation is effected. The contractor is protected against loss resulting from cancellation by contract provisions allowing reimbursement of unrecovered nonrecurring costs included In prices for canceled items.
Page 697 - Is a cooperative undertaking of the General Accounting Office, the Office of Management and Budget, the Department of...
Page 774 - Congress that such contracts, when practicable, provide for the purchase of property at times and in quantities that will result in reduced costs to the Government and provide incentives to contractors to improve productivity through investment in capital facilities, equipment, and advanced technology.
Page 167 - Additional reviews are then made by the Office of the Secretary of Defense and the Office of Management and Budget before our materiel program request is finalized.