Search Images Maps Play YouTube News Gmail Drive More »
Sign in
Books Books
" Officer grants a further period of time before the date of final payment under the contract), notifies the Contracting Officer in writing of the causes of delay. The Contracting Officer shall ascertain the facts and the extent of the delay and extend... "
Code of Federal Regulations - Page 319
1965
Full view - About this book

Cases Decided in the United States Court of Claims, Volume 111

United States. Court of Claims - Law reports, digests, etc - 1948
...the beginning of any such delay, or such longer period as may be allowed by the Contracting Officer, notify the Contracting Officer in writing of the causes...judgment the findings of fact justify such an extension. The decision of the Contracting Officer thereon shall be final, subject only to appeal under Article...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 115

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1950
...final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30 days,...
Full view - About this book

Cases Decided in the United States Court of Claims, Volume 94

United States. Court of Claims - Law reports, digests, etc - 1942
...the beginning of any such delay notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...fact justify such an extension, and his findings of facts thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30...
Full view - About this book

Cases Decided in the United States Court of Claims, Volume 105

United States. Court of Claims - Law reports, digests, etc - 1946
...liquidated damages because of unforeseeable causes of delay, including strikes, and it provides that the contracting officer "shall ascertain the facts...judgment the findings of fact justify such an extension." This, of course, makes it mandatory upon the contracting officer to make findings of fact upon an application...
Full view - About this book

Cases Decided in the United States Court of Claims, Volume 107

United States. Court of Claims - Law reports, digests, etc - 1947
...final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...of fact justify such an extension, and his findings pi fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 152

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1963
...the beginning of any such delay, or such longer period as may be allowed by the Contracting Officer, notify the Contracting Officer in writing of the causes...delay and extend the time for completing the work or any part thereof when in his judgment the findings of fact justify such an extension. The decision...
Full view - About this book

Decisions of the Comptroller General of the United States, Volume 29

United States. General Accounting Office - Finance, Public - 1950
...final settlement of the contract) notify the contracting officer in writing of the causes of delay, who shall ascertain the facts and the extent of the delay...justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal, within 30 days,...
Full view - About this book

The Code of Federal Regulations of the United States of America Having ...

Administrative law - 1939
...final settlement of the contract) notify the contracting officer In writing of the causes of delay, who shall ascertain the facts and the extent of the delay...Justify such an extension, and his findings of fact thereon shall be final and conclusive on the parties hereto, subject only to appeal within 30 days,...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1964
...capacity) , acts of another contractor in the performance of a contract with the Government, fires, floods, epidemics, quarantine restrictions, strikes,...In the clause of this contract entitled "Disputes." 1-8.710 Default clause for fixed-price research and development contracts. The following clause...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1983
...capacity), acts of another contractor in the performance of a contract with the Government, fires, floods, epidemics, quarantine restrictions, strikes,...findings of fact shall be final and conclusive on the panics hereto, subject only to appeal as provided in the clause of this contract entitled "Disputes."...
Full view - About this book




  1. My library
  2. Help
  3. Advanced Book Search
  4. Download EPUB
  5. Download PDF