" Contractor for adjustment under this clause must be asserted within sixty (60) days from the date of receipt by the Contractor of the notification of change : Provided, however. That the Contracting Officer, if he decides that the facts justify such action,... "
Code of Federal Regulations - Page 232
1965
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 154

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1968
...that the facts justify such action, may receive and act upon any such claim asserted at any time/prior to final payment under this contract. Failure to agree...Contractor from proceeding with the contract as changed. 5. Inspection (a) All supplies (which term throughout this clause includes without limitation raw materials,...
Full view - About this book

Code of Federal Regulations

Administrative law - 1965
...delivery schedule, or both, (11) In the amount of any fixed fee to be paid to the Contractor, and (111) in such other provisions of the contract as may be...contracts insert clause 3 of NASA Form 551-3 set forth in § 1816.859-4(d). LIMITATION OF COST (SEPTEMBER 1962) (a) It is estimated that the total cost to the...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1972
...or delivery schedule, or both, (2) in the amount of any feĢ to be paid to the Contractor, and (3) in such other provisions of the contract as may be...Contractor from proceeding with the contract as changed. (b) If this contract is executed by an A.IJ3. Washington Contracting Officer, valid change orders may...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1973
...equitable adjustment shall be made (1) In the contract price or time of performance, or both, and (11) In such other provisions of the contract as may be...Contractor from proceeding with the contract as changed. In the foregoing clause, the period of "sixty (60) days" within which any claim for adjustment must...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1974
...cost of delivery schedule, or both, (2) In the amount of any fee to be paid to the Contractor, and (3) in such other provisions of the contract as may be...Contractor from proceeding with the contract as changed. (b) If this contract is executed by an AID/Washington Contracting Officer, valid change orders may...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1978
...amount of any fee to be paid to the Contractor, and (iii) in such other provisions of the eontract as may be so affected, and the contract shall be modified...Contractor from proceeding with the contract as changed. In the foregoing clause, the period of "sixty (60) days" within which any claim for adjustment must...
Full view - About this book

Code of Federal Regulations

Administrative law - 1965
...equitable adjustment shall be made in the contract price, or time of performance, or both, and the contract shall be modified in writing accordingly....Contractor from proceeding with the contract as changed. [26 FR 12442, Dec. 27, 1961, as amended at 27 FR 3386, Apr. 10, 1962] § 1007.4028 Estimated requirements....
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1964
...equitable adjustment shall be made in the contract price, or time of performance, or both, and the contract shall be modified in writing accordingly....Contractor from proceeding with the contract as changed. [26 FR 12442, Dec. 27, 1961, as amended at 27 FR 3386, Apr. 10, 1962] § 1007.4028 Estimated requirements....
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1977
...an equitable adjustment shall be made in the contract price or delivery schedule (or both) and the contract shall be modified in writing accordingly....the Contractor from proceeding with the contract as modified. (b) In the foregoing clause the period of "sixty (60) days" within which any claim for adjustment...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1981
...an equitable adjustment shall be made in the contract price or delivery schedule (or both) and the contract shall be modified in writing accordingly....the Contractor from proceeding with the contract as modified. (b) In the foregoing clause the period of "sixty (60) days" within which any claim for adjustment...