Community Policy: Hearing Before the Joint Committee on Atomic Energy, Congress of the United States in Executive Session, Eighty-first Congress, Second Session on Community PolicyU.S. Government Printing Office, 1950 - Antinuclear movement |
From inside the book
Results 1-5 of 6
Page 1
... staff . Mr. DURHAM . The hearing will come to order . The Commission has a matter to discuss with the committee this morning with regard to the problem raised by the limitation placed on the appropriations bill by the Appropriations ...
... staff . Mr. DURHAM . The hearing will come to order . The Commission has a matter to discuss with the committee this morning with regard to the problem raised by the limitation placed on the appropriations bill by the Appropriations ...
Page 3
... staff for 3 or 4 years and feels he has a valid contract with the Govern- ment , then along during that period you say the contract is not any good , this is the disturbing factor . I do not know how high to rate , it , but I rate it ...
... staff for 3 or 4 years and feels he has a valid contract with the Govern- ment , then along during that period you say the contract is not any good , this is the disturbing factor . I do not know how high to rate , it , but I rate it ...
Page 10
... possible moment and the assumption on our part that this application will take time for consideration by you and your staff , leads the company to suggest that modification No. 20 be executed with the fixed fee remaining 10 COMMUNITY ...
... possible moment and the assumption on our part that this application will take time for consideration by you and your staff , leads the company to suggest that modification No. 20 be executed with the fixed fee remaining 10 COMMUNITY ...
Page 11
... staff of the Turner Construction Co. , were assigned to the work . Notwithstanding the fact that 32 additional personnel over and above the 10 initially agreed upon , were assigned to the work , the company made no request for ...
... staff of the Turner Construction Co. , were assigned to the work . Notwithstanding the fact that 32 additional personnel over and above the 10 initially agreed upon , were assigned to the work , the company made no request for ...
Page 14
... staff of both company and Commission , it is felt that the Commission should have complete assurance of the successful accom- plishment of the present objectives without further trial or experience with the company's progress in the new ...
... staff of both company and Commission , it is felt that the Commission should have complete assurance of the successful accom- plishment of the present objectives without further trial or experience with the company's progress in the new ...
Other editions - View all
Common terms and phrases
Added responsibility Alamos Appropriations Committee approval approximately Atomic Energy Commission basis believe bill BORDEN BRIEN MCMAHON budget Carbide & Carbon City Management COLE Commission's COMMITTEE ON ATOMIC Community Affairs community operation company feels concern construction contemplated in prior contract expiration contract with Carbide contract with Roane-Anderson contractor cost plus fixed course current fixed fee DURHAM effective July expense facilities fact figures give Government gross cost Hanford HOLIFIELD House industry initiated JOINT COMMITTEE June 30 KNOWLAND Los Alamos maintenance management fee management responsibility MARCH 9 MCCORMACK McMahon chairman ment method million dollars mittee modifica month Oak Ridge area officially original contract pay Roane-Anderson pay Zia percent period personnel PIKE planned plant point of order present prior fee negotiations problem procedures profit reduced reimburse request scope Senate Senate Appropriations Committee September 23 ship SHUGG staff subcontract thing tion trying VOLPE WILLIAM L WILLIAMS