Community Policy: Hearing Before the Joint Committee on Atomic Energy, Congress of the United States in Executive Session, Eighty-first Congress, Second Session on Community PolicyU.S. Government Printing Office, 1950 - Antinuclear movement |
From inside the book
Results 1-3 of 3
Page 8
... ship- building companies to build a ship at a cost plus fixed fee , that fixed fee might be 2 percent or 5 percent of the cost of the ship . The Govern ment pays all of the materials cost , it pays all of the employees ' wages on that ship ...
... ship- building companies to build a ship at a cost plus fixed fee , that fixed fee might be 2 percent or 5 percent of the cost of the ship . The Govern ment pays all of the materials cost , it pays all of the employees ' wages on that ship ...
Page 9
... ship- building and all other lines ? Mr. WILLIAMS . The way we arrived at our fees for our construc- tion management was to contact a large number of construction firms throughout the United States , well - known firms , and to get them ...
... ship- building and all other lines ? Mr. WILLIAMS . The way we arrived at our fees for our construc- tion management was to contact a large number of construction firms throughout the United States , well - known firms , and to get them ...
Page 16
... ship- yard . Right there in Oak Ridge itself is the Carbide & Carbon Co. operating the big plant for us on exactly the same basis . They get complete reimbursement and get a fixed fee . This is our normal method of operation when we are ...
... ship- yard . Right there in Oak Ridge itself is the Carbide & Carbon Co. operating the big plant for us on exactly the same basis . They get complete reimbursement and get a fixed fee . This is our normal method of operation when we are ...
Other editions - View all
Common terms and phrases
Added responsibility Alamos Appropriations Committee approval approximately Atomic Energy Commission basis believe bill BORDEN BRIEN MCMAHON budget Carbide & Carbon City Management COLE Commission's COMMITTEE ON ATOMIC Community Affairs community operation company feels concern construction contemplated in prior contract expiration contract with Carbide contract with Roane-Anderson contractor cost plus fixed course current fixed fee DURHAM effective July expense facilities fact figures give Government gross cost Hanford HOLIFIELD House industry initiated JOINT COMMITTEE June 30 KNOWLAND Los Alamos maintenance management fee management responsibility MARCH 9 MCCORMACK McMahon chairman ment method million dollars mittee modifica month Oak Ridge area officially original contract pay Roane-Anderson pay Zia percent period personnel PIKE planned plant point of order present prior fee negotiations problem procedures profit reduced reimburse request scope Senate Senate Appropriations Committee September 23 ship SHUGG staff subcontract thing tion trying VOLPE WILLIAM L WILLIAMS