to the seller by reason of the termination of work pursuant to this clause, the buyer, but without duplication of any amounts agreed upon in accordance with paragraph (d), shall pay to the seller the following amounts:

(1) For completed supplies accepted by the buyer (or sold or acquired as provided in paragraph (b) (7) above) and not theretofore paid for, forthwith a sum equivalent to the aggregate price for such supplies computed in accordance with the price or prices specified in the contract, appropriately adjusted for any saving of freight or other charges;

(2) In respect of the work terminated as permitted by this clause, the total (without duplication of any items) of—

(i) The cost of such work, including initial costs and preparatory expenses allocable thereto, exclusive of any costs attributable to supplies paid or to be paid for under (1) above; and

(ii) The cost of settling and paying claims arising out of the termination of work under subcontracts or orders as provided in paragraph (b) (5) above, exclusive of the amounts paid or payable on account of supplies or materials delivered or services furnished by the subcontractor prior to the effective date of the Notice of Termination of work under this contract, which amount shall be included in the cost on account of which payment is made under (1) above; and

(iii) A sum, as a profit, equal to 2 percent of the part of the amount determined under (1) above which represents the cost of articles and materials not processed by the seller, plus a sum equal to 8 percent of the remainder of such amount, but the aggregate of such sum shall not exceed 6 percent of the whole of the amount determined under (1) above, which amount for the purpose of this subdivision (iii) shall exclude any charges for interest on borrowings: Provided, however, That if it appears that the seller would have sustained a loss on the entire contract had it been completed, no profit shall be included or allowed under this subdivision (iii) and an appropriate adjustment shall be made reducing the amount of the settlement to reflect the indicated rate of loss; and

(3) The reasonable costs of settlement, including accounting, legal, clerical, and other expenses reasonably necessary for the preparation of settlement claims and supporting data with respect to the terminated portion of the contract and for the termination and settlement of subcontracts thereunder, together with reasonable storage, transportation, and other costs incurred in connection with the protection or disposition of the property allocable to contract.

this

The total sum to be paid to the seller under (1) and (2) above shall not exceed the total contract price as reduced by the amount of payments otherwise made and as further reduced by the contract price of work not terminated. Except for normal spoilage and except to the extent that the buyer or the Government shall have otherwise expressly assumed the risk of loss, there shall be excluded from the amounts payable to the seller under (1) and (2)(i) above the fair value as determined by the buyer of property which is destroyed, lost, stolen, or damaged so as to become undeliverable to the buyer or to a purchaser pursuant to paragraph (b) (7).

(f) The obligation of the buyer to make any payments under this clause shall be subject to deductions with respect to (1) all unliquidated advance or other payments on account theretofore made to the seller applicable to the terminated portion of this contract, (2) any claim which the buyer may have against the seller, in connection with this contract, and (3) the agreed price for, or the proceeds of sale of, any materials, supplies, or other things retained by the seller or sold, and not otherwise recovered by or credited to the buyer.

(g) If the termination hereunder be partial, prior to the settlement of the terminated portion of this contract, the seller may file with the buyer a request in writing that an equitable adjustment be made in the price or prices specified in the contract for the work in connection with the continued portion not terminated by the Notice of Termination, and the appropriate equitable adjustment shall be made in such price or prices.

(h) The buyer may, from time to time, under such terms and conditions as he may prescribe, make partial payments and payments on account against costs incurred by the seller with respect to the terminated portion of the contract, whenever in the opinion of the buyer the aggregate of such payments shall be within the amount to which the seller will be entitled hereunder. If the total of such payments is in excess of the amount finally agreed upon or determined to be due under this clause, such excess shall be payable by the seller to the buyer upon demand, together with interest computed at the rate of 6 percent per annum, for the period from the date such excess payment is received by the seller to the date on which such excess is repaid: Provided, however, That no interest shall be charged with respect to any such excess payment attributable to a reduction in the seller's claim by reason of retention or other disposition of termination inventory until ten days after the date of such retention or disposition, or such later date as determined by the buyer by reason of the circumstances.

(1) For the purpose of paragraphs (c) and (e) above, the amounts of the payments to be made by the buyer to the seller shall be determined in conformity with the policies and principles set forth in Part 1-8 of the Federal Procurement Regulations (41 CFR 1-8), in effect at the date of this contract. Unless otherwise provided for in this contract, or by applicable statute, the seller, for a period of three years after final settlement under the contract shall make available to the buyer and the Government at all reasonable times at the office of the seller all his books, records, documents, or other evidence bearing on the costs and expenses of the seller under the contract and in respect of the termination of work hereunder or, to the extent approved by the Government, photographs, microphotographs, or other authentic reproductions thereof.

§1-8.707 Default clause for fixed-price supply contracts.

The following clause is applicable as prescribed in § 1-8.700-2(b)(1):

DEFAULT

(a) The Government may, subject to the provisions of paragraph (c) below, by written notice of default to the Contractor, terminate the whole or any part of this contract in any one of the following circumstances:

(1) If the Contractor fails to make delivery of the supplies or to perform the services within the time specified herein or any extension thereof; or

(ii) If the Contractor fails to perform any of the other provisions of this contract, or so fails to make progress as to endanger performance of this contract in accordance with its terms, and in either of these two circumstances does not cure such failure within a period of 10 days (or such longer period as the Contracting Officer may authorize in writing) after receipt of notice from the Contracting Officer specifying such failure.

(b) In the event the Government terminates this contract in whole or in part as provided in paragraph (a) of this clause, the Government may procure, upon such terms and in such manner as the Contracting Officer may deem appropriate, supplies or services similar to those so terminated, and the Contractor shall be liable to the Government for any excess costs for such similar supplies or services: Provided, That the Contractor shall continue the performance of this contract to the extent not terminated under the provisions of this clause.

(c) Except with respect to defaults of subcontractors, the Contractor shall not be liable for any excess costs if the failure to perform the contract arises out of causes beyond the control and without the fault

or

negligence of the Contractor. Such causes may include, but are not restricted to, acts of God or of the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather; but in every case the failure to perform must be beyond the control and without the fault or negligence of the Contractor. If the failure to perform is caused by the default of a subcontractor, and if such default arises out of causes beyond the control of both the Contractor and subcontractor, and without the fault or negligence of either of them, the Contractor shall not be liable for any excess costs for failure to perform, unless the supplies or services to be furnished by the subcontractor were obtainable from other sources in sufficient time to permit the Contractor to meet the required delivery schedule.

(d) If this contract is terminated as provided in paragraph (a) of this clause, the Government, in addition to any other rights provided in this clause, may require the Contractor to transfer title and deliver to the Government, in the manner and to the extent directed by the Contracting Officer, (1) any completed supplies, and (ii) such partially completed supplies and materials, parts, tools, dies, jigs, fixtures, plans, drawings, information, and contract rights (hereinafter called "manufacturing materials") as the Contractor has specifically produced or specifically acquired for the performance of such part of this contract as has been terminated; and the Contractor shall, upon direction of the Contracting Officer, protect and preserve property in possession of the Contractor in which the Government has an interest. Payment for completed supplies delivered to and accepted by the Government shall be at the contract price. Payment for manufacturing materials delivered to and accepted by the Government and for the protection and preservation of property shall be in an amount agreed upon by the Contractor and Contracting Officer; failure to agree to such amount shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled "Disputes." The Government may withhold from amounts otherwise due the Contractor for such completed supplies or manufacturing materials such sum as the Contracting Officer determines to be necessary to protect the Government against loss because of outstanding liens or claims of former lien holders.

(e) If, after notice of termination of this contract under the provisions of this clause, it is determined for any reason that the Contractor was not in default under the provisions of this clause, or that the default was

excusable under the provisions of this clause, the rights and obligations of the parties shall, if the contract contains a clause providing for termination for convenience of the Government, be the same as if the notice of termination had been issued pursuant to such clause. If, after notice of termination of this contract under the provisions of this clause, it is determined for any reason that the Contractor was not in default under the provisions of this clause, and if this contract does not contain a clause providing for termination for convenience of the Government, the contract shall be equitably adjusted to compensate for such termination and the contract modified accordingly; failure to agree to any such adjustment shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled "Disputes."

(f) The rights and remedies of the Government provided in this clause shall not be exclusive and are in addition to any other rights and remedies provided by law or under this contract.

§ 1-8.708 Excusable delays clause for cost-reimbursement type contracts. The following clause is applicable as prescribed in § 1-8.700-2(c):

EXCUSABLE DELAYS

Except with respect to defaults of subcontractors, the Contractor shall not be in default by reason of any failure in performance of this contract in accordance with its terms (including any failure by the Contractor to make progress in the prosecution of the work hereunder which endangers such performance) if such failure arises out of causes beyond the control and without the fault or negligence of the Contractor. Such causes may include, but are not restricted to, acts of God or of the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather, but in every case the failure to perform must be beyond the control and without the fault or negligence of the Contractor. If the failure to perform is caused by the failure of a subcontractor to perform or make progress, and if such failure arises out of causes beyond the control of both the Contractor and subcontractor, and without the fault or negligence of either of them, the Contractor shall not be deemed to be in default, unless (a) the supplies or services to be furnished by the subcontractor were obtainable from other sources, (b) the Contracting Officer shall have ordered the Contractor in writing to procure such supplies or services from such other sources, and (c) the Contractor shall have failed to com

ply reasonably with such order. Upon request of the Contractor, the Contracting Officer shall ascertain the facts and extent of such failure and, if he shall determine that any failure to perform was occasioned by any one or more of the said causes, the delivery schedule shall be revised accordingly, subject to the rights of the Government under the clause hereof entitled Termination for Default or for Convenience of the Government.

§ 1-8.709 Default clause for fixed-price construction contracts.

§ 1-8.709-1 Long-form clause.

The following clause is applicable as prescribed in § 1-8.700-2(b)(4):

TERMINATION FOR DEFAULT-DAMAGES FOR DELAY-TIME EXTENSIONS

(a) If the Contractor refuses or fails to prosecute the work, or any separable part thereof, with such diligence as will insure its completion within the time specified in this contract, or any extension thereof, or fails to complete said work within such time, the Government may, by written notice to the Contractor, terminate his right to proceed with the work or such part of the work as to which there has been delay. In such event the Government may take over the work and prosecute the same to completion, by contract or otherwise, and may take possession of and utilize in completing the work such materials, appliances, and plant as may be on the site of the work and necessary therefor. Whether or not the Contractor's right to proceed with the work is terminated, he and his sureties shall be liable for any damage to the Government resulting from his refusal or failure to complete the work within the specified time.

(b) If fixed and agreed liquidated damages are provided in the contract and if the Government so terminates the Contractor's right to proceed, the resulting damage will consist of such liquidated damages until such reasonable time as may be required for final completion of the work together with any increased costs occasioned the Government in completing the work.

(c) If fixed and agreed liquidated damages are provided in the contract and if the Government does not so terminate the Contractor's right to proceed, the resulting damage will consist of such liquidated damages until the work is completed or accepted. (d) The Contractor's right to proceed shall not be so terminated nor the Contractor charged with resulting damage if:

(1) The delay in the completion of the work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including but not restricted to, acts of God, acts of the public

enemy, acts of the Government in either its sovereign or contractual capacity, acts of another contractor in the performance of a contract with the Government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, unusually severe weather, or delays of subcontractors or suppliers arising from unforeseeable causes beyond the control and without the fault or negligence of both the Contractor and such subcontractors or suppliers; and

(2) The Contractor, within 10 days from the beginning of any such delay (unless the Contracting Officer grants a further period of time before the date of final payment under the contract), notifies the Contracting Officer in writing of the causes of delay. The Contracting Officer shall ascertain the facts and the extent of the delay and extend the time for completing the work when, in his judgment, the findings of fact justify such an extension, and his findings of fact shall be final and conclusive on the parties subject only to appeal as provided in the clause of this contract entitled "Disputes." 1

(e) If, after notice of termination of the Contractor's right to proceed under the provisions of this clause, it is determined for any reason that the Contractor was not in default under the provisions of this clause, or that the delay was excusable under the provisions of this clause, the rights and obligations of the parties shall, if the contract contains a clause providing for termination for convenience of the Government, be the same as if the notice of termination had been issued pursuant to such clause. If, in the foregoing circumstances, this contract does not contain a clause providing for termination for convenience of the Government, the contract shall be equitably adjusted to compensate for such termination and the contract modified accordingly; failure to agree to any such adjustment shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled "Disputes."

(f) The rights and remedies of the Government provided in this clause are in addition to any other rights and remedies provided by law or under this contract.

[ocr errors][merged small][merged small][merged small]

to complete it, within the time specified, the Government may, by written notice to the Contractor, terminate his right to proceed. Thereafter, the Government may have the work completed and the Contractor shall be liable for any resulting excess cost to the Government. If the Government does not terminate the Contractor's right to proceed, he shall continue the work and shall be liable to the Government for any actual damages occasioned by such delay unless liquidated damages are stipulated.

(b) The Contractor's right to proceed shall not be terminated nor the Contractor charged with actual or liquidated damages under (a) above because of any delays in completion of the work due to causes other than normal weather, beyond his control and without his fault or negligence, including but not restricted to, acts of God, acts of the public enemy, acts of the Government (in either its sovereign or contractual capacity), acts of another contractor in the performance of a contract with the Government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather, or delays of subcontractors or suppliers due to causes beyond their control and without their fault or negligence: Provided, That the Contractor shall within 10 days from the beginning of any such delay, unless the Contracting Officer shall grant a further period of time prior to the date of final payment under the contract, notify the Contracting Officer in writing of the causes of delay and the facts relating thereto. The Contracting Officer shall consider the facts and ascertain the extent of the delay, and extend the time for completing the work when in his judgment the facts justify such an extension, and his decision shall be final and conclusive on the parties, subject only to appeal as provided in the clause of this contract entitled "Disputes."

[31 F.R. 5880, Apr. 16, 1966]

§ 1-8.710 Default clause for fixed-price research and development contracts. The following clause is applicable as prescribed in § 1-8.700-2(b) (3):

DEFAULT

(a) The Government may, subject to the provisions of paragraph (c) of this clause, by written notice of default to the Contractor, terminate the whole or any part of this contract in any one of the following cir

cumstances:

(1) If the Contractor fails to perform the work called for by this contract within the time(s) specified herein or any extension thereof; or

(2) If the Contractor fails to perform any of the other provisions of this contract, or so fails to prosecute the work as to endanger performance of this contract in accordance with its terms, and in either of

these two circumstances does not cure such failure within a period of 10 days (or such longer period as the Contracting Officer may authorize in writing) after receipt of notice from the Contracting Officer specifying such failure.

(b) in the event the Government terminates this contract in whole or in part as provided in paragraph (a) of this clause, the Government may procure, upon such terms and in such manner as the Contracting officer may deem appropriate, work similar to the work so terminated and the Contractor shall be liable to the Government for any excess costs for such similar work: Provided, That the Contractor shall continue the performance of this contract to the extent not terminated under the provisions of this clause.

(c) Except with respect to defaults of subcontractors, the Contractor shall not be liable for any excess costs if the failure to perform the contract arises out of causes beyond the control and without the fault or negligence of the Contractor. Such causes may include, but are not restricted to, acts of God or of the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather; but in every case the failure to perform must be beyond the control and without the fault or negligence of the Contractor. If the failure to perform is caused by the default of a subcontractor, and if such default arises out of causes beyond the control of both the Contractor and subcontractor, and without the fault or negligence of either of them, the Contractor shall not be liable for any excess costs for failure to perform unless the supplies or services to be furnished by the subcontractor were obtainable from other sources in sufficient time to permit the Contractor to meet the required delivery schedule or other performance requirements.

(d) If this contract is terminated as provided in paragraph (a) of this clause, the Government, in addition to any other rights provided in this clause, may require the Contractor to transfer title and deliver to the Government, in the manner and to the extent directed by the Contracting Officer, any of the completed or partially completed work not theretofore delivered to, and accepted by, the Government and any other property, including contract rights, specifically produced or specifically acquired for the performance of such part of this contract as has been terminated; and the Contractor shall, upon the direction of the Contracting Officer, protect and preserve property in the possession of the Contractor in which the Government has an interest. The Government shall pay to the Contractor the contract price, if separately stated, for completed work accepted by the Government

and the amount agreed upon by the Contractor and the Contracting Officer for (1) completed work for which no separate price is stated, (2) partially completed work, (3) other property described above which is accepted by the Government, and (4) the protection and preservation of property. Failure to agree shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled "Disputes." The Government may withhold from amounts otherwise due the Contractor for such completed supplies or manufacturing materials such sum as the Contracting Officer determines to be necessary to protect the Government against loss because of outstanding liens or claims of former lien holders.

(e) If, after notice of termination of this contract under the provisions of this clause, it is determined for any reason that the Contractor was not in default under the provisions of this clause, or that the default was excusable under the provisions of this clause, the rights and obligations of the parties shall, if the contract contains a clause providing for termination for convenience of the Government, be the same as if the notice of termination had been issued pursuant to such clause. If, after notice of termination of this contract under the provisions of this clause, it is determined for any reason that the Contractor was not in default under the provisions of this clause, and if this contract does not contain a clause providing for termination for convenience of the Government, the contract shall be equitably adjusted to compensate for such termination and the contract modified accordingly; failure to agree to any such adjustment shall be a dispute concerning a question of fact within the meaning of the clause of this contract entitled "Disputes."

(f) The right and remedies of the Government provided in this clause shall not be exclusive and are in addition to any other rights and remedies provided by law or under this contract.

Subpart 1-8.8-Formats of Notices, Forms, Warranties, and Agree

ments

§ 1-8.800 Scope of subpart.

This subpart contains certain suggested formats of notices, forms, warranties, and agreements related to the termination and settlement of contracts. The formats are for guidance of agencies in their implementation of this Part 1-8. § 1-8.801 Notice of termination for convenience of the Government.

§ 1-8.801-1 Telegraphic notice.

(a) The following format of telegraphic notice is suggested for use where