 | United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1963
...performance of this contract in accordance with its terms, and in either of these two circumstances does not cure such failure within a period of 10 days...from the Contracting Officer specifying such failure. ( b ) The Contractor shall not be liable for any excess costs if any failure to perform the contract... | |
 | United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1959
...performance of this contract in accordance with its terms, and in either of these two circumstances does not cure such failure within a period of 10 days...of notice from the Contracting Officer specifying sucn failure. (b) The Contractor shall not be liable for any excess costs if any failure to perform... | |
 | Administrative law - 1997
...not the Contractor's plant. If the Contractor falls to perform or act as required In (1) or (2) above and does not cure such failure within a period of...the Contracting Officer specifying such failure, the Government shall have the right by contract or otherwise to replace or correct such supplies and equitably... | |
 | Administrative law - 2001
...not the Contractor's plant. If the Contractor falls to perform or act as required in (1) or (2) above and does not cure such failure within a period of...the Contracting Officer specifying such failure, the Government shall have the right by contract or otherwise to replace or correct such supplies and equitably... | |
 | Administrative law - 1999
...replace them so as to endanger performance of the delivery schedule, and in either of these circumstances does not cure such failure within a period of 10 days...from the Contracting Officer specifying such failure. (ii) Instead of correction or replacement by the Government, the Contracting Officer may require an... | |
 | Administrative law - 1975
...performance of this contract in accordance with its terms, and in either of these two circumstances dews not cure such failure within a period of 10 days (or...from the Contracting Officer specifying such failure. (b) In the event the Government terminates this contract in whole or in part as provided in paragraph... | |
 | Administrative law - 1984
...them so as to endanger performance •:' the delivery schedule, and In either of theee circumstances does not cure such failure within a period of 10 days...notice from the Contracting Officer specifying such figure. (11) Instead of correction or replacement iy the Government, the Contracting Officer may require... | |
 | Administrative law - 1976
...performance of this contract in accordance with its terms, and in either of these two circumstances does not cure such failure within a period of 10 days...after receipt of notice from the Contracting Officer specilying such failure. (b) In the event the Government terminates this contract in whole or in part... | |
 | Administrative law - 1971
...of this contract in ac§ 1-8.801-1 cordance with Its terms, and in either of these two circumstances does not cure such failure within a period of 10 days...writing) after receipt of notice from the Contracting Offlcer specifying such failure. (b) in the event the Government terminates this contract in whole... | |
 | Administrative law - 1979
...failure 7-103.11 ARMED SERVICES PROCUREMENT REGULATION CONTRACT CLAUSES AND SOLICITATION PROVISIONS within a period of 10 days (or such longer period...from the Contracting Officer specifying such failure. (b) In the event the Government terminates this contract in whole or in part as provided in paragraph... | |
| |