1352.217-90 Inspection and manner of

doing work. As prescribed in 1317.7001(a), insert the following clause: INSPECTION AND MANNER OF DOING WORK

(CAR 1352.217-90) (JAN 1987) (a) All work and material shall be subject to the approval of the Contracting Officer or his duly authorized representative. Work shall be performed in accordance with the plans and specifications of this contract as modified by any contract modification.

(b) Unless otherwise specifically provided for in the contract, all operational practices of the Contractor and all workmanship and material, equipment and articles used in the performance of work shall be in accordance with American Bureau of Shipping Rules for Building and Classing Steel Vessels, U.S. Coast Guard Marine Engineering Regulations and Material Specifications (Subchapter F 46 CFR), U.S. Coast Guard Electrical Engineering Regulations (Subchapter J 46 CFR) (APR 1982), and U.S.P.H.S., Handbook on Sanitation in Vessel Construction, in effect at the time of the Contractor's submission of bid (or acceptance of the contract, if negotiated), and the best commercial maritime practices, except where military specifications are specified, in which case such standards of material and work. manship shall be followed.

(c) All material and workmanship shall be subject to inspection and test at all times during the Contractor's performance of the work to determine their quality and suitability for the purpose intended and compliance with the contract. In case any material or workmanship furnished by the Contractor is found to be defective prior to redelivery of the vessel, or not in accordanoe with the requirements of the contract, the Government shall have the right prior to redelivery of the vessel to reject such material or workmanship, and to require its correction or replacement by the Contractor at the Contractor's cost and expense. This Government right is in addition to its rights under any Guarantee clause in this contract. If the Contractor fails to proceed promptly with the replacement or correc

tion of such material or workmanship, as required by the Contracting Officer, the Government may, by contract or otherwise, replace or correct such material or workmanship and charge to the Contractor the excess cost to the Government. The Contractor shall provide and maintain an inspection system acceptable to the Government covering the work specified in the contract. Records of all inspection work by the Contractor shall be kept complete and available to the Government during the performance of the contract and for a period of 2 years after delivery of the vessel to the Government.

(d) No welding, including tack welding and brazing, shall be permitted in connection with repairs, completions, alterations, or addition to hulls, machinery or components of vessels unless the welder is at the time, qualified to the standards established by the United States Coast Guard, the American Bureau of Shipping, or the Department of the Navy. The welder's qualifications shall be appropriate for the particular service application, filler material type, position of welding, and welding process involved in the work being undertaken. A welder may be required to requalify if the Contracting Officer believes there is a reasonable doubt concerning the welder's ability. Welder's qualifications for this purpose shall be outlined in “Marine Engineering Regulations" of the United States Coast Guard. When a welding process other than manual shielded arc is proposed or required, the contractor or fabricator shall submit procedure qualification tests for approval prior to production welding. Procedure qualification tests shall be conducted in accordance with the requirements of the “Marine Engineering Regulations" of the United States Coast Guard.

(e) The Contractor shall exercise reasonable care to protect the vessel from fire, and the Contractor shall maintain a reasonable system of inspection over the activities of welders, burners, riveters, painters, plumbers and similar workers, particularly where such activities are undertaken in the vicinity of the vessel's magazine, fuel oil tanks, or storerooms containing flammable material. A reasonable number of hose lines shall be maintained by the Contractor ready for immediate use on the vessel at all times while the vessel is berthed alongside the Contractor's pier or in rydock or on a marine railway. All tanks or bilge areas under alteration or repair shall be cleaned, washed, and steamed out or otherwise made safe by the Contractor if and to the extent necessary as required by good marine practice or by current OSHA Regulations. The Contracting Officer's Technical Representative (COTR) shall be furnished with a “gas free" or "safe for hot work" or "safe for men" certificate

(1) Without additional expense to the Government, the Contractor shall employ specialty subcontractors where required by the specifications or when necessary for satisfactory performance of the work.

(m) When requested by the COTR, the Contractor shall notify the COTR in advance:

(i) Prior to starting inspections or tests; and

(ii) When supplies will be ready for Government inspection.

(n) When advance notification is requested, the authorized COTR shall specify the period and method of notification.

(End of clause)

1352.217-91 Delivery of vessel to the con

tractor. As prescribed in 1317.7001(a), insert the following clause:

before any hot work or entry is done. Unless otherwise provided in this contract, the Contractor shall at all times maintain a reasonable fire watch about the vessel, including & fire watch on the vessel while work is being performed thereon.

(f) The Contractor shall place proper safeguards and/or effect such safety precautions as necessary, including suitable and sufficient lighting, for the prevention of accidents or injury to persons or property during the prosecution of work under this contract and/or from time of receipt of the vessel until acceptance by the Government of the work performed.

(g) Except as otherwise provided in this contract, when the vessel is in the custody of the contractor or in drydock or on a marine railway and the temperature becomes as low as 35 degrees Fahrenheit, the Contractor shall keep all pipelines, fixtures, traps, tanks, and other receptacles on the vessel drained to avoid damage from freezing, or if this is not practicable, the vessel shall be kept heated to prevent such damage. The vessel's stern tube and propeller hubs shall be protected from frost damage by applied heat through the use of a salamander or other proper means, as approved by the COTR.

(h) Whenever practicable, the work shall be performed in a manner which does not interfere with the berthing and messing of personnel attached to the vessel. The Contractor shall ensure that assigned personnel have access to the vessel at all times. It is understood that such personnel will not interfere with the work or the Contractor's workers.

(i) The Government does not guarantee the correctness of the dimensions, sizes, and shapes given in any sketches, drawings, plans or specifications prepared or furnished by the Government. The Contractor shall be responsible for the correctness of the shape, sizes and dimensions of parts to be furnished hereunder, other than those furnished by the Government.

(j) The Contractor shall at all times keep the site of the work on the vessel free from accumulation of waste material or rubbish caused by Contractor employees or the work, and at the completion of the work shall remove all rubbish from and about the site of the work and shall leave the work and its immediate vicinity “broom clean" unless more exactly specified in this contract.

(k) While in drydock or on a marine railway, the Contractor shall be responsible for the closing before the end of working hours, of all valves and openings upon which work is being done by its workers when such closing is practicable. The Contractor shall keep the COTR cognizant of the closure status of all valves and openings upon which the Contractor's workers have been working.

DELIVERY OF VESSEL TO THE CONTRACTOR

(CAR 1352.217-91) (JAN 1987) (a) The Government shall deliver the vessel to the Contractor at the location specified in the contract.

(b) If the Contractor's plant is specified, it shall be understood to mean the fairway of the plant. The Contractor shall provide necessary tugs and pilot services to move the vessel from the fairway to the pier or dock and, upon completion of all work, from the pier or dock to the fairway of the plant.

(c) While the vessel is in the possession of the Contractor, any necessary movement of the vessel incidental to the work specified in the contract shall be furnished by the Contractor without additional charge to the Government.

(End of clause)

1352.217-92 Performance.

As prescribed in 1317.7001(a), insert the following clause:

PERFORMANCE (CAR 1352.217-92) (JAN 1987)

(a) Upon the issuance of the contract, the Contractor shall promptly commence the work specified in any plans and specifications made a part of the contract, and shall diligently prosecute the work to completion. The Contractor shall not commence work until the contract has been issued.

(b) The Government shall deliver the vessel described in the contract at such time and location as may be specified in the contract. Upon completion of the work, the Government shall accept delivery of the vessel at such time and location as may be specified in the contract.

(c) Without additional charge to the Government, and without specific requirement in the contract, the Contractor shall:

(1) Make available at the plant to personnel of the vessel while in drydock or on a marine railway, toilet and similar facilities acceptable to the Contracting Officer as adequate in number and sanitary standards;

(2) Supply and maintain, in such condition as the Contracting Officer may reasonably require, suitable brows and gangways from the pier, drydock or marine railway to the vessel;

(3) Treat salvage, scrap, or other ship's material of the Government resulting from performance of the work as items of Government furnished property in accordance with the Government Property clause;

(4) Perform, or pay the cost of, any repair, reconditioning or replacement made necessary as the result of the use by the Contractor of any of the vessel's machinery, equipment or fittings, including, but not limited to, winches, pumps, riggings, or pipe lines; and

(5) Furnish suitable offices, office equipment and telephones at or near the site of the work as the Contracting Officer reasonably requires for himself and his staff.

(d) Except as otherwise provided in the contract, the Contractor shall furnish all necessary material, labor, services, equipment, supplies, power, accessories, facilities, and other things and services necessary for accomplishing the work, subject to Government rights under the Government Property clause.

(e) The Contractor shall conduct dock and sea trials of the vessel as required by the contract. Unless otherwise expressly provided in the contract, during the conduct of these trials the vessel shall be under the control of the vessel's commander and crew with representatives of the Contractor and the Government on board to determine whether or not the work done by the Contractor has been satisfactorily performed. Dock and sea trials not speoified which the Contractor requires for his own benefit shall not be undertaken by the Contractor without prior notice to and approval of the Contracting Officer; any such dock or sea trial shall be conducted at the risk and expense of the Contractor. The Contractor shall provide and install all fittings and appliances which may be necessary for the dock and sea trials, to enable the representatives of the Government to determine whether the requirements of the contract plans and specifications have been met. The Contractor shall also be responsible for the care, installation and removal of any instruments and apparatus furnished by the Government for such trials.

(End of clause)

1352.217-93 Delays.

As prescribed in 1317.7001(a), insert the following clause:

DELAYS (CAR 1352.217-93) (JAN 1987) When during the performance of this contract the Contractor is required to delay the work on a vessel temporarily, due to orders or actions of the Government respecting stoppage of work to permit shifting the vessel, stoppage of hot work to permit bunkering, fueling, stoppage of work due to embarking or debarking passengers and loading or discharging cargo, and the Contractor is not given sufficient advance notice or is otherwise unable to avoid incurring additional costs on account thereof, an equitable adjustment may be made in the contract price pursuant to the Changes clause.

(End of clause)

1352.217-94 Minimization of delay due to

government furnished property. As prescribed in 1317.7001(a), insert the following clause: MINIMIZATION OF DELAY DUE TO GOVERN

MENT FURNISHED PROPERTY (CAR

1352.217-94) (JAN 1987) (a) In order to assure timely delivery of the vessel under this contract, it is imperative that delay in delivery of such vessel resulting from late, damaged, or unsuitable Government furnished property be held to an absolute minimum. In order to achieve minimization of delay it is agreed that:

(1) Subject to adjustment as provided in paragraph (b) of this clause, the Government shall deliver each item of Government furnished property to the Contractor on or before the date specified in the contract or, if later, in sufficient time for the contractor to deliver the vessel in accordance with the delivery schedule specified elsewhere.

(2) The Government may forego furnishing any item of Government property to the Contractor. In that event, the Contractor shall prepare the vessel in terms of piping, wiring, structure, foundation, ventilation, and any other preinstallation requirements of the item, so that the work on the vessel may continue without delay and disruption resulting from the absence of the item. If the Government does not furnish an item designated as Government furnished property, the parties may be entitled to an equitable adjustment in the contract price, in accordance with the Changes clause for eliminating the requirement to install the Government property item. But, notwithstanding any other clause of this contract,

an adjustment shall not be made in the delivery schedule of any vessel if the Government chooses not to furnish the item on or before the delivery date of the item. If the Government subsequently desires the Contractor to install the item prior to delivery of the vessel, a contract modification shall be executed which takes into account any increase in cost or performance time resulting from the installation.

(b) If the delivery date for the vessel is extended for any reason, the latest date for which the Government must deliver items of Government property shall be deemed to be extended by an equal number of days unless (i) the Contracting Officer agrees in writing that earlier delivery of the items is required, in which case some or all of the Government property shall be extended as agreed rather than on a day-for-day basis, or (ii) a Government property item was the exclusive cause for the extension of the delivery date of the vessel in which case the latest date by which the Government must deliver the item shall not be deemed to be extended unless the parties agree otherwise.

(c) The delivery or performance dates for the supplies or services to be furnished by the Contractor under this contract are based upon the expectation that Government furnished property suitable for use (except for such property furnished "as is") will be delivered to the Contractor at the time stated in the specification or, if not so stated, in sufficient time to enable the Contractor to meet such delivery or performance dates. If the Government furnished property is not delivered to the Contractor by such time and the Contractor makes a timely written request, the Contracting Officer shall determine if an equitable adjustment is appropriate. If determined appropriate, the Contracting Oificer shall equitably adjust the delivery or performance date, the specifications, the price, or any other contractual provision affected by any such delay, in accordance with the Changes clause.

(d) The Government Property and Minimization of Delay Due to Government Furnished Property clauses contain exclusive remedies. The Government shall not be liable to suit for breach of contract by reason of any delay in delivery of Government furnished property or delivery of such property in a condition not suitable for its intended use.

ADDITIONAL PROVISIONS RELATING TO Gov

ERNMENT PROPERTY (CAR 1352.217-95)

(JAN 1987) (a) Notwithstanding any requirements to the contrary for the furnishing of material by the Government which may appear in plans, drawings, or other data, the Government shall furnish only the material specifically listed in the specifications as Government furnished property. Any material required for the performance of the contract which does not appear in the specifications as Government furnished shall be furnished by the Contractor.

(b) The Contracting Officer may increase the amount of material to be furnished by the Government and the contract shall be equitably adjusted in accordance with the Government Property clause.

(c) Unless otherwise specifically directed by the Contracting Officer, nonreusable crates and other nonreusable packaging in which Government material is delivered to the Contractor shall become the property of the Contractor upon removal of the packaged or crated material.

(d) Any packaging in preparation for delivery or for other disposal of Government property by the Contractor at the direction or authorization of the Contracting Officer pursuant to paragraph (i) of the Government Property clause shall be provided for by change order and an appropriate adjustment shall be made in the contract price in accordance with the Changes clause.

(e) The vessel, its equipment, movable stores, cargo and other ship's material are not designated Government furnished property under

the Government Property clause.

(End of clause)

1352.217-96 Liability and insurance.

As prescribed in 1317.7001(a), insert the following clause:

LIABILITY AND INSURANCE (CAR 1352.217-96)

(JAN 1987) (a) The Contractor shall exercise reasonable care and use its best efforts to prevent accidents, injury or damage to all employees, persons and property, in and about the work, and to the vessel or part thereof upon which work is done.

(b) The Contractor shall be responsible for and make good at its own cost and expense any and all loss of or damage of whatsoever nature to the vessel (or part thereof), its equipment, movable stores and cargo, and Government owned material and equipment for the repair, completion, alteration of or addition to the vessel in the possession of the Contractor, whether at the plant or elsewhere, arising or growing out of the per

(End of clause)

1352.217-95 Additional provisions relating

to government property. As prescribed in 1317.7001(a), insert the following clause:

formance of the work, except where the Contractor can affirmatively show that such loss or damage was due to causes beyond the Contractor's control, was proximately caused by the fault or negligence of agents or employees of the Government, or which loss or damage the Contractor by exercise of reasonable care was unable to prevent. However, the Contractor shall not be responsible for any such loss or damage discovered after redelivery of the vessel unless (i) the loss or damage is discovered within 90 days after redelivery of the vessel and (ii) loss or damage is affirmatively shown to be the result of the fault or negligence of the Contractor. To induce the Contractor to perform the work for the compensation provided, it is specifically agreed that the Contractor's aggregate liability on account of loss of or damage to the vessel (or part thereof), its equipment, movable stores and cargo and Government owned materials and equipment shall in no event exceed the sum of $300,000. As to the Contractor, the Government assumes the risk of loss or damage to the Government-owned vessel (or part thereof), its equipment, movable stores and cargo and said Government-owned materials and equipment in excess of $300,000. This assumption of risk includes but is not limited to loss or damage from negligence of whatsoever degree of the Contractor's servants, employees, agents or subcontractors but specifically excludes loss or damage from willful misconduct or lack of good faith on the part of the Contractor's directors, officers and any of its managers, superintendents or other equivalent representatives who have supervision or direction of (i) all or substantially all of the Contractor's business, or (ii) all or substantially all of the Contractor's operation at any one plant. However, as to such risk assumed and borne by the Government, the Government shall be subrogated to any claim, demand or cause of action against third persons which exists in favor of the Contractor, and the contractor shall, if required, execute a formal assignment or transfer of claims, demands or causes of action. Nothing contained in this paragraph shall create or give rise to any right, privilege or power in any person except the Contractor, nor shall any person (except the Contractor) be

or become entitled thereby to proceed directly against the Government, or join the Government as a co-defendent in any action against the Contractor brought to determine the Contractor's liability, or for any other purpose.

(c) The Contractor indemnifies and holds harmless the Government, its agencies and instrumentalities, and the vessel against all suits, actions, claims, costs or demands (including without limitation, suits, actions, claims, costs or demands resulting from death, personal injury and property

damage) to which the Government, its agencies and instrumentalities, or the vessel may be subject or put by reason of damage or injury (including death) to the property or person of any one other than the Government, its agencies, instrumentalities and personnel, or the vessel arising or resulting in whole or in part from the fault, negligence, wrongful act or wrongful omission of the Contractor, or any subcontractor, its or their servants, agents or employees; provided that the Contractor's obligation to indemnify under this paragraph (c) shall not exceed the sum of $300,000 on account of any one accident or occurrence in respect of any one vessel. Such indemnity shall include, without limitation, suits, actions, claims, costs or demands of any kind whatsoever, resulting from death, personal injury or property damage occurring during the period of performance of work on the vessel or within 90 days after redelivery of the vessel. With respect to any such suits, actions, claims, costs or demands resulting from death, personal injury or property damage occurring after the expiration of such period, the rights and liabilities of the Government and the Contractor shall be as determined by other provisions of this contract and by law; provided that such indemnity shall apply to death occurring after such period which results from any personal injury received during the period covered by the Contractor's indemnity as provided herein.

(d) The Contractor shall, at its own expense, procure, and thereafter maintain such casualty, accident and liability insurance, in such forms and amounts as may be approved by the Contracting Officer, insuring the performance of its obligations under paragraph (c) of this clause. In addition, the Contractor shall at its own expense procure and thereafter maintain such ship repairer's legal liability insurance as may be necessary to insure the Contractor against its liability as ship repairer in the amount of $300,000, or the value of the vessel as determined by the Contracting Officer, whichever is the lesser, with respect to each vessel on which work is performed. The Contractor shall cause the Government to be named as an additional insured under any and all liability insurance policies. However, at the discretion of the Contracting Officer, such insurance need not be procured whenever the job order requires work on parts of a vessel only and the work is to be performed at a plant other than the site of the vessel. Further, the Contractor shall procure and maintain in force Workmen's Compensation Insurance (or its equivalent) covering its employees engaged in the work and shall insure the procurement and maintenance of such insurance by all subcontractors engaged in the work. The Contractor shall