" Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change : Provided, however, That the Contracting Officer, if he decides that the facts justify such action, may... "
Code of Federal Regulations: Containing a Codification of Documents of ... - Page 301
1975
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 154

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1968 - 922 pages
...writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor...clause of this contract entitled "Disputes." However, nothing in this clause shall excuse the Contractor from proceeding with the contract as changed. *****...
Full view - About this book

Cases Decided in the United States Court of Claims ... with ..., Volume 141

United States. Court of Claims, Audrey Bernhardt - Law reports, digests, etc - 1959 - 1028 pages
...in writing within 30 days from the date of receipt by the Contractor of the notification of extra or change : Provided, however, That the Contracting Officer,...upon any such claim asserted at any time prior to the date of final settlement of the contract. If the parties fail to agree upon the adjustment to be...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1982 - 690 pages
...contract shall be modified in writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within thirty (30) days...clause of this contract entitled "Disputes". However, nothing In this clause shall excuse the Contractor from proceeding with the contract as changed. The...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1965 - 1168 pages
...Any claim by the Contractor for adjustment under this clause must be asserted within sixty (60) days from the date of receipt by the Contractor of the...clause of this contract entitled "Disputes." However, nothing In this clause shall excuse the Contractor from proceeding with the contract as changed. §...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1969 - 752 pages
...contract shall be modified In writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within thirty (30) days...to any adjustment shall be a dispute concerning a question of fact within the meaning of the "Disputes" clause of this contract. However, nothing In...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1983 - 1104 pages
...contract shall be modified in writing accordingly. Any claim by the Contractor for adjustment under this clause must be asserted within thirty (30) days...to any adjustment shall be a dispute concerning a question of fact within the meaning of the "Disputes" clause of this contract. However, nothing in...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1974 - 1028 pages
...under this clause must be aeserted within sIxty (60) days from the date of receipt by the Con¿ tractor of the notificatIon of change: Provid,ed, however,...of this contract entitled “Disputes.” However, nothing in this clause shall excuse the Contractor from proceeding with the contract as changed. In...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1978 - 188 pages
...of receipt by the Contractor of the notification Title 41 — Public Contracts, Property Management of change: Provided, however, that the Contracting...clause of this contract entitled "Disputes". However, nothing in this clause shall excuse the Contractor from proceeding with the contract as changed. (b)...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1972 - 914 pages
...Any claim by the Contractor for adjustment under this clause must be asserted within sixty (60) days from the date of receipt by the Contractor of the...to any adjustment shall be a dispute concerning a question of fact within the meaning of the clause of thla contract entitled "Disputes". However, nothing...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1972 - 1094 pages
...of receipt by the Contractor of the notification of change; Provided, however, That the Contractlng Officer, if he decides that the facts justify such...clause of this contract entitled "Disputes." However, nothing In this clause shall excuse the Contractor from proceeding with the contract as changed. In...
Full view - About this book