ance, or other requirement, which is prescribed under this Act (other than this section, or section 111 (b), 112, or 303) or contained in an applicable implementation plan (other than a requirement imposed under authority described in section 110 (a) (2) (F) (v)), and which limits, or is designed to limit, stationary source emissions resulting from combustion of fuels, including a prohibition on, or specification of, the use of any fuel of any type, grade, or pollution characteristic.

(2) The term 'air pollution requirement' means any emission limitation, schedule or timetable for compliance, or other requirement, which is prescribed under any Federal, State, or local law or regulation, including this Act (except for any requirement prescribed under subsection (c) or (d) of this section, section 110(a) (2) (F) (v), or section 303), and which limits stationary source emissions resulting from combustion of fuels (including a prohibition on, or specification of, the use of any fuel of any type, grade, or pollution characteristic).

66

(3) The terms 'stationary source' and 'source' have the same. meaning as the term 'stationary source' has under section 111 (a) (3); except that such terms include any owner or operator (as defined in section 111 (a) (5)) of such source.

"(4) The term 'coal' includes coal derivatives.

"(5) The term 'primary standard conditions' means a limitation, requirement, or other measure, prescribed by the Administrator under subsection (d) (2) (A) of this section.

"(6) The term 'regional limitation' means the requirement of subsection (c) (2) (D) of this section.

"(b) (1) (A) The Administrator may, for any period beginning on or after the date of enactment of this section and ending on or before June 30, 1975, temporarily suspend any stationary source fuel or emission limitation as it applies to any person

"(i) if the Administrator finds that such person will be unable to comply with any such limitation during such period solely because of unavailability of types or amounts of fuels (unless such unavailability results from an order under section 2(a) of the Energy Supply and Environmental Coordination Act of 1974),

or

"(ii) if such person is a source which is described in subsection (c) (1) (A) or (B) of this section and which has converted to coal, and the Administrator finds that the source will be able to comply during the period of the suspension with all primary standard conditions which will be applicable to such source. Any suspension under this paragraph, the imposition of any interim requirement on which such suspension is conditioned under paragraph (3) of this subsection, and the imposition of any primary standard condition which relates to such suspension, shall be exempted from any procedural requirements set forth in this Act or in any other provision of Federal, State, or local law; except as provided in subparagraph (B) of this paragraph.

"(B) The Administrator shall give notice to the public and afford interested persons an opportunity for written and oral presentations of data, views, and arguments prior to issuing a suspension under subparagraph (A), or denying an application for such a suspension, un

less otherwise provided by the Administrator for good cause found and published in the Federal Register. In any case, before issuing such a suspension, he shall give actual notice to the Governor of the State in which the affected source or sources are located, and to appropriate local governmental officials (as determined by the Administrator). The issuing or denial of such a suspension, the imposition of an interiin requirement, and the imposition of any primary standard condition shall be subject to judicial review only on the grounds specified in paragraph (2) (B), (2) (C), or (2) (D), of section 700 or titie 5, United States Code, and shall not be subject to any proceeding under section 304 (a) (2) or 307 (b) and (c) of this Act.

"(2) In issuing any suspension under paragraph (1), the Administrator is authorized to act on his own motion or upon application by any person (including a public officer or public agency).

66

(3) Any suspension under paragraph (1) shall be conditioned upon compliance with such interim requirements as the Administrator determines are reasonable and practicable. Such interim requirements shall include, but need not be limited to, (A) a requirement that the persons receiving the suspension comply with such reporting requirements as the Administrator determines may be necessary, (B) such measures as the Administrator determines are necessary to avoid an imminent and substantial endangerment to health of persons and (C) in the case of a suspension under paragraph (1)(A)(i), requirements that the suspension shall be inapplicable during any period during which fuels which would enable compliance with the suspended stationary source fuel or emission limitations are in fact reasonably available (as determined by the Administrator) to such person.

"(c) (1) Except as provided in paragraph (2) of this subsection, the Administrator shall issue a compliance date extension to any fuelburning stationary source

(A) which is prohibited from using petroleum products or natural gas by reason of an order which is in effect under section 2 (a) and (b) of the Energy Supply and Environmental Coordination Act of 1974, or

"(B) which the Administrator determines began conversion to the use of coal as its primary energy source during the period beginning on September 15, 1973, and ending on March 15, 1974. and which, on or after September 15, 1973, converts to the use of coal as its primary energy source. If a compliance date extension is issued to a source, such source shall not, until January 1, 1979, be prohibited, by reason of the application of any air pollution requirement, from burning coal which is available to such source, except as provided in subsection (d) (3). For purposes of this paragraph, the term 'began conversion' means action by the source during the period beginning on September 15, 1973, and ending on March 15, 1974 (such as entering into a contract binding on such source for obtaining coal, or equipment or facilities to burn coal: expanding substantial sums to permit such source to burn coal; or applying for an air pollution variance to enable such source to burn coal) which the Administrator finds evidences a lecision (made prior to March 15, 1974) to convert to burning coal as a result of the unavailability of an adequate supply of fuels required for compliance with the applicable implementation plan, and a good faith effort to expeditiously carry out such decision.

"(2) (A) A compliance date extension under paragraph (1) of this subsection may be issued to a source only if—

(i) the Administrator finds that such source will not be able to burn coal which is available to such source in compliance with all applicable air pollution requirements without a compliance date extension,

(ii) the Administrator finds that the source will be able during the period of the compliance date extension to comply with all the primary standard conditions which are required under subsection (d) (2) to be applicable to such source, and with the regional limitation if applicable to such source, and

(iii) the source has submitted to the Administrator a plan for compliance for such source which the Administrator has approved.

A plan submitted under clause (iii) of the preceding sentence shall be approved only if it meets the requirements of regulations prescribed under subparagraph (B). The Administrator shall approve or disapprove any such plan within 60 days after such plan is submitted.

"(B) Not later than 90 days after the date of enactment of this section, the Administrator shall prescribe regulations requiring that any source to which a compliance date extension applies submit and obtain approval of its means for and schedule of compliance with the requirements of subparagraph (C) of this paragraph. Such regulations shall include requirements that such schedules shall include dates by which any such source must

"(i) enter into contracts (or other obligations enforceable against such source) which the Administrator has approved as being adequate to provide for obtaining a long-term supply of coal which enables such source to achieve the emission reduction required by subparagraph (C), or

"(ii) if coal which enables such source to achieve such emission reduction is not available to such source, enter into contracts (or other obligations enforceable against such source) which the Administrator has approved as being adequate to provide for obtaining (I) a long-term supply of other coal, and (II) continuous emission reduction systems necessary to permit such source to burn such coal, and to achieve the degree of emission reduction required by subparagraph (C).

Regulations under this subparagraph shall provide that contracts or other obligations required to be approved under this subparagraph must be approved before they are entered into (except that a contract or obligation which was entered into before the date of enactment of this section may be approved after such date).

"(C) Regulations under subparagraph (B) shall require that the source achieve the most stringent degree of emission reduction that such source would have been required to achieve under the applicable implementation plan which was in effect on the date of submittal (under subparagraph (B) of this paragraph) of the means for and schedule of compliance (or if no applicable implementation plan was in effect on such date, under the first applicable implementation plan which takes effect after such date). Such degree of emission reduction shall be achieved as soon as practicable, but not later than

December 31, 1978; except that, in the case of a source for which a continuous emission reduction system is required for sulfur-related emissions, reduction of such emissions shall be achieved on a date designated by the Administrator (but not later than January 1, 1979). Such regulations shall also include such interim requirements as the Administrator determines are reasonable and practicable, including requirements described in subparagraphs (A) and (B) of subsection (b) (3) and requirements to file progress reports.

"(D) A source which is issued a compliance date extension under this subsection, and which is located in an air quality control region in which a national primary ambient air quality standard for an air pollutant is not being met, may not emit such pollutants in amounts which exceed any emission limitation (and may not violate any other requirement) which applies to such source, under the applicable implementation plan for such pollutant. For purposes of this subparagraph, applicability of any such limitation or requirement to a source shall be determined without regard to this subsection or subsection (b).

"(3) A source to which this subsection applies may, upon the expiration of a compliance date extension, receive a one-year postponement of the application of any requirement of an applicable implementation plan under the conditions and in the manner provided in section 110(f).

"(4) The Administrator shall give notice to the public and afford an opportunity for oral and written presentations of data, views, and arguments before issuing any compliance date extension, prescribing any regulation under paragraph (2) of this subsection, making any finding under paragraph (2) (A) of this subsection, imposing any requirement on a source pursuant to paragraph (2) or any regulation thereunder, prescribing a primary standard condition under subsection (d) (2) which applies to a source to which an extension is issued under this subsection, or acting on any petition under subsection (d) (2) (C).

"(d) (1) (A) Whenever the Federal Energy Administrator issues an order under section 2(a) of the Energy Supply and Environmental Coordination Act of 1974 which will not apply after June 30, 1975, the Administrator of the Environmental Protection Agency shall certify to him—

"(i) in the case of a source to which no suspension will be issued under subsection (b), the earliest date on which such source will be able to burn coal and to comply with all applicable air pollution requirements, or

"(ii) in the case of a source to which a suspension will be issued under subsection (b) of this section, the date determined under paragraph (2) (B) of this subsection.

"(B) Whenever the Federal Energy Administrator issues an order under section 2(a) of such Act which will apply after June 30, 1975, the Administrator of the Environmental Protection Agency shall notify him if such source will be able, on and after July 1, 1975, to burn coal and to comply with all applicable air pollution requirements without a compliance date extension under subsection (c). If such notification is not given

[blocks in formation]

"(i) in the case of a source which is eligible for a compliance date extension under subsection (c), the Administrator of the Environmental Protection Agency shall certify to the Federal Energy Administrator the date determined under paragraph (2) (B) of this subsection, and

"(ii) in the case of a source which is not eligible for such an extension, the Administrator of the Environmental Protection Agency shall certify to the Federal Energy Administrator the earliest date on which the source will be able to burn ccal and to comply with all applicable air pollution requirements.

"(2) (A) The Administrator of the Environmental Protection Agency, after consultation with appropriate States, shall prescribe (and may from time to time, after such consultation, modify) emission limitations, requirements respecting pollution characteristics of coal, or other enforceable measures for control of emissions, for each source to which a suspension under subsection (b) (1) (A) (ii) will apply, and for each source to which a compliance date extension under subsection (c) (1) will apply. Such limitations, requirements, and measures shall be those which he determines must be complied with by the source in order to assure (throughout the period that the suspension or extension will be in effect) that the burning of coal by such source will not result in emissions which cause or contribute to concentrations of any air pollutant in excess of any national primary ambient air quality standard for such pollutant.

"(B) Whenever the Administrator prescribes a limitation, requirement, or measure under subparagraph (A) of this paragraph with respect to a source, he shall determine the earliest date on which such source will be able to comply with such limitation, requirement, or measure, and with any regional limitation applicable to such source. "(C) An air pollution control agency may petition the Administrator (A) to modify any limitation, requirement, or other measure under this paragraph so as to assure compliance with the requirements of this paragraph, or (B) to issue to the Federal Energy Administration the certification described in paragraph (3) (B) on the grounds described in clause (iii) thereof. The Administrator shall take the action requested in the petition, or deny the petition, within 90 days after the date of receipt of the petition.

"(3) (A) If the Administrator determines that a source to which a suspension under subsection (b) (1) (A) (ii) or to which a compliance date extension under subsection (c) (1) applies is not in compliance with any primary standard condition, or that a source to which a compliance date extension applies is not in compliance with a regional limitation applicable to it, he shall (except as provided in subparagraph (B)) either

"(i) enforce compliance with such condition or limitation under section 113, or

"(ii) (after notice to the public and affording an opportunity for interested persons to present data, views, and arguments, including oral presentations, to the extent practicable) revoke such suspension or compliance date extension.

"(B) If the Administrator finds that for any period

"(i) a source, to which an order under section 2(a) of the Energy Supply and Environmental Coordination Act of 1974