... furnishing information to the com- mittee . We will ask you , General Wray , first of all , to tell us how these items at the Norton Air Force Base happen to be before the committee at this time . General WRAY . In your letter of ...
... furnishing information to the com- mittee . We will ask you , General Wray , first of all , to tell us how these items at the Norton Air Force Base happen to be before the committee at this time . General WRAY . In your letter of ...
Page 2
... furnished to us by the Corps of Engineers in that area . Mr. DAVIS . Each of these three items are now scheduled to be awarded in May if proper clearance is provided by the necessary com- mittees ; is that correct ? General WRAY . Yes ...
... furnished to us by the Corps of Engineers in that area . Mr. DAVIS . Each of these three items are now scheduled to be awarded in May if proper clearance is provided by the necessary com- mittees ; is that correct ? General WRAY . Yes ...
Page 4
... furnish to the committee a statement showing the estimates which you previously submitted to this committee , and the actual contracts now under award . Mr. McCLOUD . Do you mean the estimates as of November , and as of the date of ...
... furnish to the committee a statement showing the estimates which you previously submitted to this committee , and the actual contracts now under award . Mr. McCLOUD . Do you mean the estimates as of November , and as of the date of ...
Page 6
... furnish us with further justification this morning . The first of those items is an item at the Dover Air Force Base , for a hospital . I believe at that time the committee questioned you on this project the clearance that you needed ...
... furnish us with further justification this morning . The first of those items is an item at the Dover Air Force Base , for a hospital . I believe at that time the committee questioned you on this project the clearance that you needed ...
Page 20
... furnish that to the com- mittee . I think we better furnish that to the committee . Normally I think it would be between $ 7 million and $ 8 million . Mr. CEDERBERG . Then we can reduce that package cost by the difference between ...
... furnish that to the com- mittee . I think we better furnish that to the committee . Normally I think it would be between $ 7 million and $ 8 million . Mr. CEDERBERG . Then we can reduce that package cost by the difference between ...
Other editions - View all
Common terms and phrases
acreage acres in fee acres of land AFRTC Air Force Base AIR FORCE Printed Air Force Reserve aircraft amount approximately apron Asensio's letter award date basement Billy Mitchell Field BLACK Budget CEDERBERG Chairman CLARENCE CANNON clearance Colonel Buckner Colonel PRICE committee in November COMMITTEE ON APPROPRIATIONS Communication building Contract award control room Corps of Engineers DAVIS Dover Air Force Ellsworth engine test estimated explosion fair market value February feet FRANK SANDERS fungus furnish going gunite hangar hospital at Dover indicated isolated area last spring Little Rock located matter referred McCLOUD mess Michigan JOHN MILLET HAND million nonappropriated funds Paine Air Force Paine Field Plattsburg practiced ditching present Public Law 209 purchase RABAUT recreational facilities request requirements Reserve Training Center Reserve unit resettlement charges RILEY rotometers runway Secretary of Defense Snohomish County station storage SUBCOMMITTEE swimming pools taxiway test cells Tinker Air Force unobligated warehouse WRAY