Page 4
... difference is arrived at by taking that from the approximate $ 10 million . The amount which we have unobligated is represented , largely , in savings , and we have a program showing the original estimates before bids , and after bids ...
... difference is arrived at by taking that from the approximate $ 10 million . The amount which we have unobligated is represented , largely , in savings , and we have a program showing the original estimates before bids , and after bids ...
Page 5
... difference is a part of the unobligated $ 10,581,950 as of February 1. Work yet to be awarded has a total estimated value of $ 2,218,000 for a total of $ 27,233,000 . The surplus , therefore , in the program as a result of low bids ...
... difference is a part of the unobligated $ 10,581,950 as of February 1. Work yet to be awarded has a total estimated value of $ 2,218,000 for a total of $ 27,233,000 . The surplus , therefore , in the program as a result of low bids ...
Page 10
... difference in size of the two pools . Mr. HAND . Very likely , but it was a nice , big pool , and a fair - sized installation . Is it necessary to have these pools built of dimensions permitting them to be used in AAU swimming ...
... difference in size of the two pools . Mr. HAND . Very likely , but it was a nice , big pool , and a fair - sized installation . Is it necessary to have these pools built of dimensions permitting them to be used in AAU swimming ...
Page 20
... difference between $ 725,000 and $ 2,500,000 ? General WRAY . Probably more . Mr. BLACK . We can subtract about $ 1,200,000 from that because these facilities will take the place of new construction . General WRAY . I think you ought to ...
... difference between $ 725,000 and $ 2,500,000 ? General WRAY . Probably more . Mr. BLACK . We can subtract about $ 1,200,000 from that because these facilities will take the place of new construction . General WRAY . I think you ought to ...
Other editions - View all
Common terms and phrases
acreage acres in fee acres of land AFRTC Air Force Base AIR FORCE Printed Air Force Reserve aircraft amount approximately apron Asensio's letter award date basement Billy Mitchell Field BLACK Budget CEDERBERG Chairman CLARENCE CANNON clearance Colonel Buckner Colonel PRICE committee in November COMMITTEE ON APPROPRIATIONS Communication building Contract award control room Corps of Engineers DAVIS Dover Air Force Ellsworth engine test estimated explosion fair market value February feet FRANK SANDERS fungus furnish going gunite hangar hospital at Dover indicated isolated area last spring Little Rock located matter referred McCLOUD mess Michigan JOHN MILLET HAND million nonappropriated funds Paine Air Force Paine Field Plattsburg practiced ditching present Public Law 209 purchase RABAUT recreational facilities request requirements Reserve Training Center Reserve unit resettlement charges RILEY rotometers runway Secretary of Defense Snohomish County station storage SUBCOMMITTEE swimming pools taxiway test cells Tinker Air Force unobligated warehouse WRAY