Hidden fields
Books Books
" Procurement Regulation, as it may be amended from time to time, the Contractor may submit to the Contracting Officer a list, certified as to quantity and quality, of any or all items of termination Inventory not previously disposed of, exclusive of Items... "
Code of Federal Regulations: Containing a Codification of Documents of ... - Page 137
1983
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1982 - 712 pages
...by this Letter Contract or paid in such other manner as the Contracting Officer may direct; (viit) complete performance of such part of the work as shall...storage agreement covering them. Not later than fifteen (15) days thereafter, the Government will accept such items and remove them or enter into a storage...
Full view - About this book

The Code of Federal Regulations of the United States of America

Administrative law - 1973 - 968 pages
...direct, for the protection and preservation of the property related to this Letter Contract which U in the possession of the Contractor and In which the...storage agreement covering them. Not later than fifteen (15) days thereafter, the Government will accept such Items and remove them or enter into a storage...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1974 - 1028 pages
...Immediately with the performance of the above obilga. tions notwithstanding any delay in deterS mining the amount of any items of reimbursable cost, under...storage agreement covering them. Not later than fifteen (15) days thereafter, the Government will accept such items and remove them or enter into a storage...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1983 - 1974 pages
...any time after expiration of the plant clearance period, as defined in Section VIII. Armed Services Procurement Regulation, as it may be amended from...agreement covering the same; provided, that the list submilted shall be subject to verification by the Contracting Officer upon removal of the items, or...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1968 - 1518 pages
...delay In determining or adjusting the amount of the fee, or any item of reimbursable cost, under thl¿ clause. At any time after expiration of the plant...storage agreement covering them. Not later than fifteen (15) days thereafter, the Government will accept such items and remove them or enter into a storage...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1980 - 976 pages
...is in the possession of the Contractor and in which the Government has or may acquire an interest. At any time after expiration of the plant clearance...storage agreement covering them. Not later than fifteen (15) days thereafter, the Government will accept title to such items and remove them or enter into...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1978 - 944 pages
...or adjusting the amount of the fee, or any item of reimbursable cost, under this clause. At any lime after expiration of the plant clearance period, as...storage agreement covering them. Not later than fifteen (15) days thereafter, the Government will accept such items and remove them or enter into a storage...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1967 - 1448 pages
...of reimbursable cost, under this clause. At any time after expiration of the plant clearance penod, as defined in Part 8, NASA Procurement Regulation,...storage agreement covering them. Not later than fifteen ( 15) days thereafter, the Government will accept such items and remove them or enter into a storage...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1965 - 1168 pages
...reimbursable cost, under this clause. At any time after expiration of the plant clearance period, as denned In Part 8, NASA Procurement Regulation, as It may...storage agreement covering them. Not later than fifteen (15) days thereafter, the Government will accept such Items and remove them or enter Into a storage...
Full view - About this book

Code of Federal Regulations: Containing a Codification of Documents of ...

Administrative law - 1982 - 1316 pages
...of the plant clearance period, as defined in Section VIII, Armed Services Procurement Regulation/as it may be amended from time to time, the Contractor...fifteen (IS) days thereafter, the Government will accept title to such items and remove them or enter into a storage agreement covering the same; provided,...
Full view - About this book




  1. My library
  2. Help
  3. Advanced Book Search
  4. Download EPUB
  5. Download PDF