(17) Subadvances. Substantially the following provision should be included in the contract when subadvances are contemplated:

......

Subject to the prior written approval of the Administering Office, funds from the Special Bank Account may be used by the Contractor to make advance payments or down payments to subcontractors and materialmen in advance of performance by the subcontractor or materialman. Such subadvances shall not exceed percent of the subcontract price or estimated cost as the case may be, and the subcontractors or materialmen to whom such advances are made shall furnish adequate security therefor. Unless other security is required by the Administering Office, covenants in subcontracts, expressly made for the benefit of the Government providing for a Special Bank Account for the subadvance, with Government lien thereon, and providing for a Government lien, paramount to all other liens, on all property under such subcontract, and imposing upon the subcontractor and the depository bank substantially the same duties and giving the Government substantially the same rights as are provided herein (and in the Agreement for Special Bank Account supplementary hereto) between the Government, the Contractor and the Bank, may be considered as adequate security for such subadvance.

(18) Covenants. The following are examples of some special provisions (subject to modification to adapt to the circumstances of individual cases) that may be utilized when and to the extent deemed appropriate in particular cases.

During the period of time that advance payments may be made hereunder and so long as any such advance payments remain unliquidated, the Contractor shall not, without the prior written consent of the Administering Office:

(a) Mortgage, pledge, or otherwise encumber, or suffer to be encumbered, any of the assets of the contractor now owned or hereafter acquired by him, or permit any preexisting mortgages, liens, or other encumbrances to remain on or attach to any assets of the Contractor which are allocated to the performance of this contract and with respect to which the Government has a lien hereunder;

(b) Sell, assign, transfer, or otherwise dispose of accounts receivable, notes or claims for money due or to become due;

(c) Declare or pay any dividends, except dividends payable in stock of the corporation, or make any other distribution on account of any shares of his capital stock, or purchase, redeem, or otherwise acquire for value any such stock, except as required by sinking fund or redemption arrangements reported to the Administering Office incident to the establishment of these advance payment provisions;

(d) Sell, convey, or lease all or a substantial part of his assets;

(e) Acquire for value the stock or other securities of any corporation, municipality, or governmental authority, except direct obligations of the United States;

(f) Make any advance or loan to or incur any liability as guarantor, surety, or accommodation endorser for any other firm, person, or corporation;

(g) Permit a writ of attachment or any similar process to be issued against his property without procuring release thereof or bonding the same within 30 days after the entry of the writ of attachment or any similar process;

(h) Pay any salaries, commissions, bonuses, or other remuneration in any form or manner to his directors, officers, or key employees in excess of existing rates of payments or of rates provided in existing agreements, in connection with which notice has been given to the Administering Office, or accrue such excess remuneration without first obtaining an agreement subordinating the same to all claims of the Government hereunder, or employ any person at a rate of compensation in excess of $... per annum.

(i) Make any substantial change in management, ownership, or control of the corporation; (j) Merge or consolidate with any other firm or corporation, change the type of his business or engage in any transaction outside the ordinary course of his business as presently conducted; (k) Deposit any of his funds except in a bank or trust company insured by the Federal Deposit Insurance Corporation;

(1) Create or incur indebtedness for borrowed money or advances other than advances to be made hereunder, except as specified herein;

$.

(m) Make or covenant himself to make capital expenditures exceeding in the aggregate

(n) Permit his net current assets, calculated in accordance with generally accepted accounting principles, to become less than $...

.............., or

(0) Make any payments on account of the obligations listed below, except in the manner and to the extent herein provided.

(End of clause)

7-104.35 Progress Payments. In accordance with E-510, insert one of the following clauses:

(a) Progress Payment Clause for Other Than Small Business Concerns.

Any change, addition, or deletion to this clause is subject to the prior approval requirements outlined in Appendix E, Part 2.

PROGRESS PAYMENT FOR OTHER THAN SMALL BUSINESS CONCERNS (1974 APR) Progress payments shall be made to the Contractor when requested as work progresses, but not more frequently than bi-weekly in amounts approved by the Contracting Officer upon the following terms and conditions:

(a) Computation of Amounts.

(1) Unless a smaller amount is requested, each progress payment shall be (i) eighty percent (80%) of the amount of the Contractor's total costs which, except as provided herein with respect to costs of pension contributions, shall include only those recorded costs which result, at the time of the request, from payment made by cash, check, or other form of actual payment for items or services purchased directly for the contract, together with (when the Contractor is not delinquent in payment of costs of contract performance in the ordinary course of business) costs incurred, but not necessarily paid, for materials which have been issued from the Contractor's stores inventory and placed in the production process for use on the contract, for direct labor, for direct travel, for other direct inhouse costs, and for properly allocable and allowable indirect costs, all as shown by records maintained by the Contractor for purposes of obtaining payment under Government contracts plus (ii) the amount of progress payments which have been paid to Contractor's subcontractors and other divisions as provided in (j) below; all less the sum of previous progress payments. With respect to costs of pension contributions, when pension contributions are paid by the Contractor to the retirement fund less frequently than quarterly, accruals of the costs of these pension contributions shall be excluded from Contractor's total costs for progress payment purposes until such costs are paid. If pension contributions are paid on a quarterly or more frequent basis, accruals of the costs of these pension contributions may be included in Contractor's total costs for progress payment purposes provided that the pension contributions are paid to the retirement fund within thirty (30) days after the close of the period covered by the payment. If payments are not made to the fund within such thirty (30) day period, pension contribution costs shall be excluded from Contractor's total costs for progress payment purposes until payment therefor has been made.

(2) The Contractor's total costs ((a)(1)(i)) shall be reasonable, allocable to this contract, and consistent with sound and generally accepted accounting principles and practices. However, such costs shall not include (i) any costs incurred by subcontractors or suppliers, or (ii) any payments or amounts payable to subcontractors or suppliers, except for completed work (including partial deliveries) to which the Contractor has acquired title and except for amounts paid or payable under cost-reimbursement or time and material subcontracts for work to which the Contractor has acquired title, or (iii) costs ordinarily capitalized and subject to depreciation or amortization except for the properly depreciated or amortized portion of such costs.

(3) The amount of unliquidated progress payments shall not exceed the lesser of (i) eighty percent (80%) of the costs mentioned in (a)(1)(i) above, plus any unliquidated progress payments mentioned in item (a)(1)(ii) above, both of which are applicable only to the supplies and services not yet delivered and invoiced to and accepted by the Government, or (ii) 80 percent of the total contract price of supplies and services not yet delivered and invoiced to and accepted by the Government, less unliquidated advance payments.

(4) The aggregate amount of progress payments made shall not exceed eighty percent (80%) of the total contract price.

(5) If at any time a progress payment or the unliquidated progress payments exceed the amount permitted by this paragraph (a), the Contractor shall pay the amount of suc. excess to the Government upon demand.

(b) Liquidation. Except as provided in the clause entitled "Termination for Convenience of the Government," all progress payments shall be liquidated by deducting from any payment under this contract, other than advance or progress, the amount of unliquidated progress payments, or eighty percent* (80%) (See footnote at end of clause) of the gross amount invoiced, whichever is less. Repayment to the Government required by a retroactive price reduction will be made after calculating liquidations and payments on past invoices at the reduced prices and adjusting the unliquidated progress payments accordingly. The Government reserves the right to unilaterally change from the ordinary liquidation rate to the alternate rate when deemed appropriate for proper contract financing.

(c) Reduction or Suspension. The Contracting Officer may reduce or suspend progress payments, or liquidate them at a rate higher than the percentage stated in (b) above, or both, whenever he finds upon substantial evidence that the Contractor (i) has failed to comply with any material requirement of this contract, (ii) has so failed to make progress, or is in such unsatisfactory financial condition, as to endanger performance of this contract, (iii) has allocated inventory to this contract substantially exceeding reasonable requirements, (iv) is delinquent in payment of the costs of performance of this contract in the ordinary course of business, (v) has so failed to make progress that the unliquidated progress payments exceed the fair value of the work accomplished on the undelivered portion of this contract, or (vi) is realizing less profit than the estimated profit used for establishing a liquidation percentage in paragraph (b), if that liquidation percentage is less than the percentage stated in paragraph (a)(1).

(d) Title. Immediately, upon the date of this contract, title to all parts; materials; inventories; work in process; special tooling as defined in the clause of this contract entitled "Special Tooling"; special test equipment and other special tooling to which the Government is to acquire title pursuant to any other provision of this contract; nondurable (i.e., noncapital) tools, jigs, dies, fixtures, molds, patterns, taps, gauges, test equipment, and other similar manufacturing aids title to which is not obtained as special tooling pursuant to this paragraph; and drawings and technical data (to the extent delivery thereof to the Government is required by other provisions of this contract); theretofore acquired or produced by the Contractor and allocable or properly chargeable to this contract under sound and generally accepted accounting principles and practices shall forthwith vest in the Government; and title to all like property thereafter acquired or produced by the Contractor and allocable or properly chargeable to this contract as aforesaid shall forthwith vest in the Government upon said acquisition, production or allocation. Notwithstanding that title to property is in the Government through the operation of this clause, the handling and disposition of such property shall be determined by the applicable provisions of this contract such as: the Default clause and paragraph (h) of this clause; Termination for Convenience of the Government clause; and the Special Tooling clause. Current production scrap may be sold by the Contractor without approval of the Contracting Officer and the proceeds shall be credited against the costs of contract performance. With the consent of the Contracting Officer and on terms approved by him, the Contractor may acquire or dispose of property to which title is vested in the Government pursuant to this clause, and in that event, the costs allocable to the property so transferred from this contract shall be eliminated from the costs of contract performance and the Contractor shall repay to the Government (by cash or credit memorandum) an amount equal to the unliquidated progress payments allocable to the property so transferred. Upon completion of performance of all the obligations of the Contractor under this contract, including liquidation of all progress payments hereunder, title to all property (or the proceeds thereof) which had not been delivered to, and accepted by the Government under this contract or which had not been incorporated in supplies delivered to and accepted by the Government under this contract and to which title has vested in the Government under this clause shall vest in the Contractor. The provisions of this contract referring to or defining liability for Government-furnished property shall not apply to property to which the Government shall have acquired title solely by virtue of the provisions of this clause.

(e) Risk of Loss. Except to the extent that the Government shall have otherwise expressly assumed the risk of loss of property, title to which vests in the Government pursuant to this clause, in the event of the loss, theft or destruction of or damage to any such property before its delivery to and acceptance by the Government, the Contractor shall bear the risk of loss and shall repay the Government an amount equal to the unliquidated progress payments based on costs allocable to such lost, stolen, destroyed or damaged property.

(f) Control of Costs and Property. The contractor shall maintain an accounting system and controls adequate for the proper administration of this clause.

(g) Reports-Access to Records. Insofar as pertinent to the administration of this clause, the Contractor will (i) furnish promptly such relevant reports, certificates, financial statements, and other information as may be reasonably requested by the Contracting Officer, and (ii) give the Government reasonable opportunity to examine and verify his books, records and accounts.

(h) Special Provisions Regarding Default. If this contract is terminated pursuant to the clause entitled "Default," (i) the Contractor shall, upon demand, pay to the Government the amount of unliquidated progress payments and (ii) with respect to all property as to which the Government elects not to require delivery under the clause entitled "Default," title shall vest in the Contractor upon full liquidation of progress payments, and the Government shall be liable for no payment except as provided by the "Default" clause.

(i) Reservations of Rights. The rights and remedies of the Government provided in this clause shall not be exclusive, and are in addition to any other rights and remedies provided by law or under this contract. No payment, or vesting of title pursuant to this clause, shall excuse the Contractor from performance of his obligations under this contract, nor constitute a waiver of any of the rights and remedies of the parties under this contract. No delay or failure of the Government in exercising any right, power or privilege under this clause shall affect any such right, power or privilege, nor shall any single or partial exercise thereof preclude or impair any further exercise thereof or the exercise of any other right, power or privilege of the Government. (j) Progress Payments to Subcontractors.

(1) The amounts mentioned in item (a)(1)(ii) above shall be all progress payments paid by the Contractor to his subcontractors or other divisions and remaining unliquidated when under subcontracts or interdivisional orders which conform to (2) below.

(2) Subcontractors or interdivisional orders on which progress payments to subcontractors or other divisions may be included in the base for progress payments pursuant to paragraph (a) of this clause are limited to those subcontracts in which there is expected to be a long “lead time,” between the beginning of work and the first delivery, approximating four months or more for small business concerns and six months or more for firms which are not small business concerns, and in which the provisions regarding progress payments (i) are substantially similar to and as favorable to the Government as this "Progress Payment" clause, no more favorable to the subcontractor or the other division than this clause is to the Contractor and on a basis of not more than eighty percent (80%) of total costs (except that in the case of those subcontractors which are small business concerns a "Progress Payment" clause substantially similar to 7-104.35(b) may be used); and (ii) make all rights of the subcontractor with respect to all property to which the Government has title under the subcontract subordinate to the rights of the Government to require delivery of such property to it in the event of default by the Contractor under this contract or in the event of the bankruptcy or insolvency of the subcontractor.

(3) The Government agrees that any proceeds received by it from property to which it has acquired title by virtue of such provisions in any subcontract shall be applied to reduce the amount of unliquidated progress payments made by the Government to the Contractor under this contract. In the event the Contractor fully liquidates such progress payments made by the Government to him hereunder and there are progress payments to any subcontractors which are unliquidated, the Contractor shall be subrogated to all the Government's rights by virtue of such provisions in the subcontract or subcontracts involved as if all such rights had been thereupon assigned and transferred to the Contractor.

(4) To facilitate small business participation in subcontracting under this contract, the Contractor agrees to offer and provide progress payments to those subcontractors which are small business concerns, in conformity with the standards for customary progress payments stated in paragraph 503 of Appendix E of the Armed Services Procurement Regulation, as in effect on the date of this contract. The Contractor further agrees that the need for such progress payments will not be considered as a handicap or adverse factor in the award of subcontracts.

(End of clause)

*For lower percentages for this paragraph (b) and for (a)(3)(ii) and (a)(4), See E-512.2.

(b) Progress Payment Clause for Small Business Concerns.

Any change, addition, or deletion to this clause is subject to the prior approval requirements outlined in Appendix E, Part 2.

PROGRESS PAYMENT FOR SMALL BUSINESS CONCERNS (1973 SEP)

Progress payments shall be made to the Contractor when requested as work progresses, but not more frequently than bi-weekly, in amounts approved by the Contracting Officer under the following terms and conditions.

(a) Computation of Amounts.

(1) Unless a smaller amount is requested, each progress payment shall be (i) eighty-five percent (85%) of the amount of the Contractor's total costs incurred under this contract, except as provided herein with respect to costs of pension contributions, plus (ii) the amount of progress payments to subcontractors as provided in (j) below; all less the sum of previous progress payments. With respect to costs of pension contributions, when pension contributions are paid by the Contractor to the retirement fund less frequently than quarterly, accruals of the costs of these pension contributions shall be excluded from Contractor's total costs for progress payment purposes until such costs are paid. If pension contributions are paid on a quarterly or more frequent basis, accruals of the costs of these pension contributions may be included in Contractor's total costs for progress payment purposes provided that the pension contributions are paid to the retirement fund within thirty (30) days after the close of the period covered by the payment. If payments are not made to the fund within such thirty-day period, pension contribution costs shall be excluded from Contractor's total costs for progress payment purposes until payment therefor has been made.

(2) The Contractor's total costs ((a)(1)(i)) shall be reasonable, allocable to this contract, and consistent with sound and generally accepted accounting principles and practices. However, such costs shall not include (i) any costs incurred by subcontractors or suppliers, or (ii) any payments or amounts payable to subcontractors or suppliers, except for completed work (including partial deliveries) to which the Contractor has acquired title and except for amounts paid or payable under cost-reimbursement or time and material subcontracts for work to which the Contractor has acquired title, or (iii) costs ordinarily capitalized and subject to depreciation or amortization except for the properly depreciated or amortized portion of such costs.

(3) The amount of unliquidated progress payments shall not exceed the lesser of (i) eightyfive percent (85%) of the costs mentioned in (a)(1)(i) above, plus any unliquidated progress payments mentioned in item (a)(1)(ii) above, both of which are applicable only to the supplies and services not yet delivered and invoiced to and accepted by the Government, or (ii) 85 percent of the total contract price of supplies and services not yet delivered and invoiced to and accepted by the Government, less unliquidated advance payments.

(4) The aggregate amount of progress payments made shall not exceed eighty-five percent (85%) of the total contract price.

(5) If at any time a progress payment or the unliquidated progress payments exceed the amount permitted by this paragraph (a), the Contractor shall pay the amount of such excess to the Government upon demand.

(b) Liquidation. Except as provided in the clause entitled "Termination for Convenience of the Government," all progress payments shall be liquidated by deducting from any payment under this contract, other than advance or progress, the amount of unliquidated progress payments, or eighty-five percent* (85%) of the gross amount invoiced, whichever is less. Repayment to the Government required by a retroactive price reduction will be made after calculating liquidations and payments on past invoices at the reduced prices and adjusting the unliquidated progress payments accordingly.

(c) Reduction or Suspension. The Contracting Officer may reduce or suspend progress payments, or liquidate them at a rate higher than the percentage stated in (b) above, or both, whenever he finds upon substantial evidence that the Contractor (i) has failed to comply with any material requirement of this contract, (ii) has so failed to make progress, or is in such unsatisfactory financial condition, as to endanger performance of this contract, (iii) has allocated inventory to this contract substantially exceeding reasonable requirements, (iv) is delinquent in payment of